1372 E 18TH ST 90021

Certificate Information: 1372 E 18TH ST 90021

Application / Permit
22016-10000-06148
Plan Check / Job No.
B22LA03784
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
1. RENOVATIONS OF EXISTING WAREHOUSE/MANUFACTURING BUILDING FOR NEW COFFEE ROASTING FACILITY. NO CHANGE OF USE. 2. INSTALLATION OF ROASTING AND ASSOCIATED EQUIPMENT. 3. RENOVATE OF PARTIAL EXISTING RESTROOMS. 4. NEW HANDICAP LIFT NEXT TO LANDING. 5. ADD DAS PARKING SPACE.
Permit Issued
Issued on 10/20/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 QUAN NGHIEM
Corrections Issued 3/29/2022 QUAN NGHIEM
Quality Review Completed 3/30/2022 KEN GILL
Building Plans Picked Up 4/1/2022 APPLICANT
Disabled Access Plans Picked Up 4/4/2022 APPLICANT
Applicant returned to address corrections 7/26/2022 QUAN NGHIEM
Plan Check Approved 8/25/2022 QUAN NGHIEM
Issued 10/20/2022 APPLICANT
Green Plans Picked Up 6/12/2023 APPLICANT
CofO in Progress 12/21/2023 KATY RAMIREZ
CofO Issued 12/22/2023 ERNESTO CORRAL
Permit Finaled 12/22/2023 ERNESTO CORRAL

Permit Application Clearance Information

Redevelopment Project Area Cleared 4/28/2022 SUSAN WONG
Eng Process Fee Ord 176,300 Cleared 7/25/2022 CINDY QI
Sewer availability Cleared 7/25/2022 CINDY QI
Food establishment approval Cleared 7/26/2022 LACDHS APPROVED
Green Code Cleared 8/4/2022 AARON COSTA
DAS Clearance Cleared 8/18/2022 QUAN NGHIEM

Contact Information

Contractor Analog Construction; Lic. No.: 1058496-B 1910 W SUNSET BLVD #660      LOS ANGELES, CA 90026

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/23/2022 Corrections Issued ALAN MORELOS
Footing/Foundation/Slab 11/29/2022 Partial Approval ALAN MORELOS
Footing/Foundation/Slab 1/11/2023 Approved ALAN MORELOS
Light Gage Steel Frame 7/21/2023 No Access for Inspection ALAN MORELOS
Wood Frame 7/21/2023 No Access for Inspection ALAN MORELOS
Light Gage Steel Frame 7/24/2023 Approved ALAN MORELOS
Wood Frame 7/24/2023 Approved ALAN MORELOS
Drywall Nailing 8/1/2023 Partial Approval ALAN MORELOS
Drywall Nailing 8/11/2023 Partial Approval KATY RAMIREZ
Final 9/25/2023 Not Ready for Inspection DARRYL ARNOLD
Green Building Final 9/25/2023 Conditional Approval DARRYL ARNOLD
Green Building Rough 9/25/2023 Conditional Approval DARRYL ARNOLD
Reinforced Masonry Frame 9/25/2023 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 9/25/2023 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 9/25/2023 Corrections Issued DARRYL ARNOLD
Final 10/23/2023 Not Ready for Inspection KATY RAMIREZ
Green Building Final 10/23/2023 Approved KATY RAMIREZ
Green Building Rough 10/23/2023 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 10/23/2023 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 10/23/2023 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 11/1/2023 Corrections Issued KATY RAMIREZ
Final 12/13/2023 Not Ready for Inspection KATY RAMIREZ
Reinforced Masonry Frame 12/13/2023 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 12/13/2023 SGSOV Approved KATY RAMIREZ
Smoke Detectors 12/13/2023 Partial Inspection KATY RAMIREZ
Final 12/19/2023 Partial Inspection KATY RAMIREZ
Smoke Detectors 12/19/2023 Approved KATY RAMIREZ
Final 12/21/2023 OK to Issue CofO KATY RAMIREZ