6200 N VARIEL AVE 1A 91367

Certificate Information: 6200 N VARIEL AVE 1A 91367

Application / Permit
22016-10000-06144
Plan Check / Job No.
B22LA03776
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Beauty Shop or Parlor
Work Description
CHANGE OF USE FROM OFFICE/ RETAIL TO HAIR SALON AND TENANT IMPROVEMENT
Permit Issued
Issued on 6/10/2022
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 ARSALAN SHABESTARI
Corrections Issued 3/15/2022 ARSALAN SHABESTARI
Quality Review Completed 3/16/2022 SAI KHUM
Green Plans Picked Up 3/18/2022 APPLICANT
Disabled Access Plans Picked Up 4/6/2022 APPLICANT
Plan Check Approved 6/7/2022 ARSALAN SHABESTARI
Issued 6/10/2022 APPLICANT
CofO in Progress 1/5/2023 BRIAN KELLY
CofO Issued 1/19/2023 JEFFREY DURAN
Permit Finaled 1/19/2023 JEFFREY DURAN

Permit Application Clearance Information

Sewer availability Cleared 3/19/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/29/2022 CARLOS AGUILERA
Green Code Cleared 4/27/2022 AARON COSTA
ZA Case Cleared 4/28/2022 YINGSHI HUANG
Specific Plan Cleared 5/12/2022 KRISTINE JEGALIAN
Miscellaneous Cleared 5/16/2022 YINGSHI HUANG
Miscellaneous Cleared 5/16/2022 YINGSHI HUANG
Specific Plan Cleared 5/18/2022 SHEILA AHORAIAN
Specific Plan Cleared 5/18/2022 SHEILA AHORAIAN
DAS Clearance Cleared 5/24/2022 ARSALAN SHABESTARI

Contact Information

Contractor Larson S K Inc; Lic. No.: 518350-B P O BOX 615      COOL, CA 95614

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 6/28/2022 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 8/19/2022 No Access for Inspection DANIEL VARNUM
Light Gage Steel Frame 8/19/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 8/31/2022 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 8/31/2022 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 9/14/2022 Approved DANIEL VARNUM
T-Bar Ceiling 10/27/2022 Approved DANIEL VARNUM
Final 12/8/2022 Not Ready for Inspection KENNETH ROBERTS
Green Building Final 12/8/2022 Not Ready for Inspection KENNETH ROBERTS
Green Building Rough 12/8/2022 Not Ready for Inspection KENNETH ROBERTS
Reinforced Masonry Frame 12/8/2022 Not Ready for Inspection KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 12/8/2022 SGSOV Approved KENNETH ROBERTS
Smoke Detectors 12/8/2022 Not Ready for Inspection KENNETH ROBERTS
Final 12/13/2022 Not Ready for Inspection DANIEL VARNUM
Green Building Final 12/13/2022 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 12/13/2022 Not Ready for Inspection DANIEL VARNUM
Reinforced Masonry Frame 12/13/2022 Not Ready for Inspection DANIEL VARNUM
Smoke Detectors 12/13/2022 Not Ready for Inspection DANIEL VARNUM
Final 12/16/2022 Not Ready for Inspection BRIAN KELLY
Green Building Final 12/16/2022 Not Ready for Inspection BRIAN KELLY
Green Building Rough 12/16/2022 Not Ready for Inspection BRIAN KELLY
Reinforced Masonry Frame 12/16/2022 Not Ready for Inspection BRIAN KELLY
Smoke Detectors 12/16/2022 Not Ready for Inspection BRIAN KELLY
Final 12/21/2022 Partial Inspection BRIAN KELLY
Green Building Final 12/21/2022 Approved BRIAN KELLY
Green Building Rough 12/21/2022 Approved BRIAN KELLY
Reinforced Masonry Frame 12/21/2022 Approved BRIAN KELLY
Smoke Detectors 12/21/2022 Approved BRIAN KELLY
Final 1/5/2023 OK to Issue CofO BRIAN KELLY