1645 S WESTERN AVE 90006

Certificate Information: 1645 S WESTERN AVE 90006

Application / Permit
22016-10000-06140
Plan Check / Job No.
B22LA03769
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Gymnasium
Work Description
CHANGE OF USE FROM RETAIL TO GYM FACILITIES FOR (E) TWO-STORY BUILDG. NEW PARTITION WALLS, TOILET, SHOWERS AND LOCKER ROOM NO CHANGE IN PARKING
Permit Issued
Issued on 9/1/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 SERGIO GUTIERREZ
Corrections Issued 3/30/2022 SERGIO GUTIERREZ
Quality Review Completed 3/30/2022 FARUK SEZER
Green Plans Picked Up 3/31/2022 APPLICANT
Building Plans Picked Up 4/11/2022 APPLICANT
Disabled Access Plans Picked Up 5/2/2022 APPLICANT
Applicant returned to address corrections 6/28/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 8/18/2022 SERGIO GUTIERREZ
Plan Check Approved 8/24/2022 SERGIO GUTIERREZ
Issued 9/1/2022 APPLICANT
TCO Issued (Expire Date: 09-30-2023) 4/3/2023 ERNESTO CORRAL
CofO in Progress 4/20/2023 ERNESTO CORRAL
CofO Issued 4/21/2023 ERNESTO CORRAL
Permit Finaled 4/21/2023 ERNESTO CORRAL

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 4/14/2022 RAFAEL FONTES
Miscellaneous Cleared 4/14/2022 RAFAEL FONTES
Miscellaneous Cleared 4/14/2022 RAFAEL FONTES
ZA Case Cleared 4/14/2022 RAFAEL FONTES
Green Code Cleared 6/13/2022 AARON COSTA
Fire Marshal Fire Life Safety Cleared 7/27/2022 MENOA AGHAJANI
DAS Clearance Cleared 8/9/2022 SERGIO GUTIERREZ

Contact Information

Architect Khorramian,, Abdy; Lic. No.: C13138 4741 LAUREL CANYON BLVD      VALLEY VILLAGE, CA 91607
Contractor Pitts Steve Construction; Lic. No.: 872321-B 25656 CALLE LA FUENTE      SAN JUAN CAPISTRANO, CA 92675
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/6/2022 Approved TIMOTHY BUXTON
Wood Frame 9/23/2022 Partial Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 9/29/2022 Conditional Approval MICHAEL ROSENBERG
Wood Frame 9/30/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 10/12/2022 Partial Approval TIMOTHY BUXTON
Wood Frame 10/27/2022 Not Ready for Inspection TIMOTHY BUXTON
Deputy Reinf. Concrete 10/28/2022 Conditional Approval MICHAEL ROSENBERG
Wood Frame 11/1/2022 Approved TIMOTHY BUXTON
Wood Frame 11/15/2022 Approved TIMOTHY BUXTON
Interior/Exterior Lathing 11/28/2022 Approved TIMOTHY BUXTON
Interior/Exterior Lathing 12/7/2022 Partial Approval RONALD JIMENEZ
Final 12/23/2022 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 12/23/2022 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Final 12/23/2022 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 12/23/2022 SGSOV Not Ready RAMAZANALI ALMASI
Smoke Detectors 12/23/2022 Not Ready for Inspection RAMAZANALI ALMASI
T-Bar Ceiling 1/18/2023 Corrections Issued KATY RAMIREZ
Pre-Inspection 1/26/2023 Partial Inspection KATY RAMIREZ
Pre-Inspection 1/30/2023 Partial Inspection KATY RAMIREZ
Pre-Inspection 2/27/2023 Partial Inspection KATY RAMIREZ
Final 3/24/2023 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 3/24/2023 Partial Inspection RAMAZANALI ALMASI
METHANE-Final 3/24/2023 Partial Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 3/24/2023 SGSOV Approved RAMAZANALI ALMASI
Smoke Detectors 3/24/2023 Partial Inspection RAMAZANALI ALMASI
Final 3/29/2023 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 3/29/2023 Approved RAMAZANALI ALMASI
METHANE-Final 3/29/2023 Not Ready for Inspection RAMAZANALI ALMASI
Smoke Detectors 3/29/2023 Approved RAMAZANALI ALMASI
Final 3/31/2023 Conditional Approval RAMAZANALI ALMASI
METHANE-Final 3/31/2023 Approved RAMAZANALI ALMASI
Special/Order Compliance 3/31/2023 Approved RAMAZANALI ALMASI
Final 4/20/2023 Conditional Approval RAMAZANALI ALMASI