202 1/2 E 108TH ST 90061
Certificate Information: 202 1/2 E 108TH ST 90061
- Application / Permit
- 22016-10000-06081
- Plan Check / Job No.
- B22LA03720
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTION OF (E) GARAGE TO ADU OF 360 SQ FT PER WFPP
- Permit Issued
- Issued on 4/15/2022
- Issuing Office
- Current Status
- CofO Issued on 3/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2022 | JOSEPH RAFOLS |
| Corrections Issued | 3/4/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 4/7/2022 | JOSEPH RAFOLS |
| Issued | 4/15/2022 | APPLICANT |
| Building Plans Picked Up | 4/19/2022 | APPLICANT |
| CofO in Progress | 3/12/2026 | ARTHUR NEGRETE |
| Permit Finaled | 3/25/2026 | ANSON MAGLASANG |
| CofO Issued | 3/25/2026 | ANSON MAGLASANG |
| Permit Finaled | 3/25/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 3/24/2022 | CINDY QI |
| Sewer availability | Cleared | 3/24/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/31/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 10/31/2022 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 10/31/2022 | Not Ready for Inspection | JOHN KLARIN |
| Piling/Pier/Caisson | 10/31/2022 | Not Ready for Inspection | JOHN KLARIN |
| Deputy Reinf. Concrete | 12/29/2022 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 1/3/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 1/3/2023 | Not Ready for Inspection | JOHN KLARIN |
| Piling/Pier/Caisson | 1/3/2023 | Not Ready for Inspection | JOHN KLARIN |
| Pre-Inspection | 1/3/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/4/2026 | Approved | ARTHUR NEGRETE |
| Final | 2/4/2026 | Corrections Issued | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 2/4/2026 | SGSOV Not Required | ARTHUR NEGRETE |
| Smoke Detectors | 2/4/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 2/9/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 2/9/2026 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 2/9/2026 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 2/9/2026 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 3/5/2026 | Corrections Issued | BEN MOLSTAD |
| Final | 3/5/2026 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 3/5/2026 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 3/5/2026 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 3/11/2026 | Approved | ARTHUR NEGRETE |
| Final | 3/11/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| HVAC-Final | 3/11/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 3/11/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 3/11/2026 | Approved | ARTHUR NEGRETE |