3942 S STEVELY AVE 90008
Certificate Information: 3942 S STEVELY AVE 90008
- Application / Permit
- 22016-10000-05895
- Plan Check / Job No.
- B22LA03566
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: RETROFIT SOFT STORY OPEN FRONT PARKING GARAGE WITH LIVING UNITS ABOVE IN ACCORDANCE WITH THE NEW SOFT STORY (DIV. '93) ORDINANCE - 183893 - RETROFIT ( ADD (N)-(2) SPECIAL CANTILEVERED COLUMNS)
- Permit Issued
- Issued on 9/22/2022
- Issuing Office
- Current Status
- CofC Issued on 2/27/2023
Permit Application Status History
| Submitted | 3/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2022 | JESSE VIDUYA |
| Corrections Issued | 4/1/2022 | JESSE VIDUYA |
| Quality Review Completed | 4/6/2022 | SAI KHUM |
| Applicant returned to address corrections | 4/15/2022 | JESSE VIDUYA |
| Applicant returned to address corrections | 5/10/2022 | JESSE VIDUYA |
| Plan Check Approved | 5/17/2022 | JESSE VIDUYA |
| Issued | 9/22/2022 | APPLICANT |
| OK for CofC | 2/23/2023 | DARRYL ARNOLD |
| CofC Issued | 2/27/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/24/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 8232 GARVEY AVE 203 ROSEMEAD, CA 91770 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/14/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/27/2022 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 10/27/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 10/27/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/2/2022 | Corrections Issued | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/4/2022 | Corrections Issued | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/9/2022 | Corrections Issued | DARRYL ARNOLD |
| Final | 12/2/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 12/2/2022 | Corrections Issued | DARRYL ARNOLD |
| Final | 1/30/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 1/30/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 1/30/2023 | Corrections Issued | DARRYL ARNOLD |
| Final | 2/23/2023 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 2/23/2023 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 2/23/2023 | Approved | DARRYL ARNOLD |