1845 S HIGHLAND AVE 90019
Certificate Information: 1845 S HIGHLAND AVE 90019
- Application / Permit
- 22016-10000-05894
- Plan Check / Job No.
- B22LA03562
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) DETACHED 2-CAR GARAGE TO ADU PER CA GC 65852.2(e)(1)(A).
- Permit Issued
- Issued on 12/22/2022
- Issuing Office
- Current Status
- CofO Issued on 5/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2022 | VIVIAN LAO |
| Corrections Issued | 3/2/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 4/5/2022 | VIVIAN LAO |
| Plan Check Approved | 4/22/2022 | VIVIAN LAO |
| Issued | 12/22/2022 | APPLICANT |
| CofO Issued | 5/17/2024 | DEROLD HAUFF |
| Permit Finaled | 5/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/30/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 3/30/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 3/30/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2022 | CHRISTOPHER ROCHA |
| Construction within easement | Cleared | 4/22/2022 | RIDWAN HARDY |
Contact Information
| Architect | Kim,, Peter Sung Taek; Lic. No.: NA29012 | , |
| Contractor | A R M Builders Inc; Lic. No.: 915352-B | , |
| Contractor | Aaron'S Pro Flooring; Lic. No.: 915352-B | , |
| Engineer | Kwon,, Ohsung; Lic. No.: NA85429 | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/19/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 4/19/2023 | Partial Approval | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 7/13/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 8/11/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 8/11/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/11/2023 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 8/23/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 8/29/2023 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Partial Approval | LILIANA PORTILLO |
| Insulation | 9/6/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 9/6/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 9/11/2023 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 9/11/2023 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 9/11/2023 | Approved | JEFFREY MEAD |
| Insulation | 9/13/2023 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 10/2/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 10/2/2023 | Conditional Approval | JOSE AVILA |
| Green Building Rough | 10/2/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 10/24/2023 | Approved | JOSH MEISTER |
| Drywall Nailing | 1/3/2024 | Approved | RONNIE MINDANAO |
| Final | 1/3/2024 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 1/3/2024 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Approved | RONNIE MINDANAO |
| Smoke Detectors | 1/3/2024 | Approved | RONNIE MINDANAO |
| Final | 1/8/2024 | Corrections Issued | RONNIE MINDANAO |
| Service/Power Release | 1/10/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Final | 1/22/2024 | Approved | STUART CHAPMAN |
| Final | 1/22/2024 | Conditional Approval | STUART CHAPMAN |
| HVAC-Final | 1/22/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 1/22/2024 | Approved | STUART CHAPMAN |