1713-1715 W 53RD ST 90062

Certificate Information: 1713-1715 W 53RD ST 90062

Application / Permit
22016-10000-05726
Plan Check / Job No.
B22LA03452
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert PORTION OF existing SFD into ADU. No additional square-footage will be added. ATTACHED ADU PER STATE LAW
Permit Issued
Issued on 5/19/2022
Issuing Office
Current Status
CofO Issued on 2/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 CARLOS MONTES
Corrections Issued 3/3/2022 CARLOS MONTES
Applicant returned to address corrections 3/29/2022 CARLOS MONTES
Plan Check Approved 5/17/2022 CARLOS MONTES
Issued 5/19/2022 APPLICANT
CofO in Progress 2/4/2025 BARRY HACHE
Permit Finaled 2/9/2025 DEROLD HAUFF
CofO Issued 2/9/2025 DEROLD HAUFF
Permit Finaled 2/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/6/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/6/2022 JEANETTE VONG
Sewer availability Cleared 5/6/2022 JEANETTE VONG
Community Plan Implem. Overlay Cleared 5/16/2022 RAFAEL FONTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/4/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 11/18/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 3/14/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/14/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/13/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 5/15/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 5/22/2023 No Access for Inspection SABAS ALONSO
Wood Frame 5/31/2023 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 6/7/2023 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 9/22/2023 Corrections Issued SABAS ALONSO
HVAC-Rough 1/9/2024 Approved MICHAEL LEWIS
Wood Frame 1/11/2024 Approved ENRIQUE MIRELES
Insulation 1/16/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 2/6/2024 No Access for Inspection RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Corrections Issued RONNIE MINDANAO
Drywall Nailing 2/9/2024 Corrections Issued RONNIE MINDANAO
Drywall Nailing 2/15/2024 Approved RONNIE MINDANAO
HVAC-Final 1/13/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 1/13/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 1/13/2025 SGSOV Not Ready BARRY HACHE
BUILDING-Rough-Frame 1/27/2025 Approved BARRY HACHE
ELECTRICAL-Final 1/27/2025 Corrections Issued BARRY HACHE
HVAC-Final 1/27/2025 Approved BARRY HACHE
PLUMBING-Final 1/27/2025 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 1/27/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Final 1/30/2025 Not Ready for Inspection BARRY HACHE
Final 1/30/2025 Not Ready for Inspection BARRY HACHE
HVAC-Final 1/30/2025 Approved BARRY HACHE
PLUMBING-Final 1/30/2025 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 1/30/2025 SGSOV Not Ready BARRY HACHE
Smoke Detectors 1/30/2025 Approved BARRY HACHE
ELECTRICAL-Final 2/3/2025 Approved BARRY HACHE
Final 2/3/2025 Not Ready for Inspection BARRY HACHE
HVAC-Final 2/3/2025 Approved BARRY HACHE
PLUMBING-Final 2/3/2025 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 2/3/2025 SGSOV Not Ready BARRY HACHE
Final 2/4/2025 OK to Issue CofO BARRY HACHE
PLUMBING-Final 2/4/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 2/4/2025 SGSOV Approved BARRY HACHE
Service/Power Release 2/4/2025 Approved BARRY HACHE