1713-1715 W 53RD ST 90062
Certificate Information: 1713-1715 W 53RD ST 90062
- Application / Permit
- 22016-10000-05726
- Plan Check / Job No.
- B22LA03452
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert PORTION OF existing SFD into ADU. No additional square-footage will be added. ATTACHED ADU PER STATE LAW
- Permit Issued
- Issued on 5/19/2022
- Issuing Office
- Current Status
- CofO Issued on 2/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | CARLOS MONTES |
| Corrections Issued | 3/3/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 3/29/2022 | CARLOS MONTES |
| Plan Check Approved | 5/17/2022 | CARLOS MONTES |
| Issued | 5/19/2022 | APPLICANT |
| CofO in Progress | 2/4/2025 | BARRY HACHE |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
| CofO Issued | 2/9/2025 | DEROLD HAUFF |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/6/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 5/6/2022 | JEANETTE VONG |
| Community Plan Implem. Overlay | Cleared | 5/16/2022 | RAFAEL FONTES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/4/2022 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/18/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 3/14/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/14/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/13/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 5/15/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/22/2023 | No Access for Inspection | SABAS ALONSO |
| Wood Frame | 5/31/2023 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/7/2023 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 9/22/2023 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 1/9/2024 | Approved | MICHAEL LEWIS |
| Wood Frame | 1/11/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 1/16/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 2/6/2024 | No Access for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2024 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 2/9/2024 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 2/15/2024 | Approved | RONNIE MINDANAO |
| HVAC-Final | 1/13/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 1/13/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 1/13/2025 | SGSOV Not Ready | BARRY HACHE |
| BUILDING-Rough-Frame | 1/27/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 1/27/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 1/27/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 1/27/2025 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 1/27/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 1/30/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 1/30/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 1/30/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 1/30/2025 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 1/30/2025 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 1/30/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 2/3/2025 | Approved | BARRY HACHE |
| Final | 2/3/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 2/3/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 2/3/2025 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Not Ready | BARRY HACHE |
| Final | 2/4/2025 | OK to Issue CofO | BARRY HACHE |
| PLUMBING-Final | 2/4/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Approved | BARRY HACHE |
| Service/Power Release | 2/4/2025 | Approved | BARRY HACHE |