22740 W CREOLE ROAD 91364

Certificate Information: 22740 W CREOLE ROAD 91364

Application / Permit
22016-10000-05675
Plan Check / Job No.
B22LA03434
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) 2-STORY SFD AND REPAIR BALCONY.
Permit Issued
Issued on 6/7/2022
Issuing Office
Current Status
Permit Finaled on 2/22/2023

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/7/2022 FERNANDO FLORES
Corrections Issued 3/8/2022 FERNANDO FLORES
Applicant returned to address corrections 3/31/2022 GEORGE ALVAREZ
Building Plans Picked Up 4/1/2022 APPLICANT
Applicant returned to address corrections 4/13/2022 RACHEL BEYENE
Plan Check Approved 5/13/2022 MINA HABILI
Issued 6/7/2022 APPLICANT
Permit Finaled 2/21/2023 TROY SANDERS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/2/2022 VASIL MIHALEV

Contact Information

Contractor Luxe Development Inc; Lic. No.: 993473-B 329 N WETHERLY DRIVE #205      BEVERLY HILLS, CA 90211
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 8/17/2022 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 8/17/2022 Corrections Issued PETER FOLLING
Deputy Drilled-In Anchors 8/31/2022 No Access for Inspection PETER FOLLING
Excavation/Setback/Form/Re-Bar 10/5/2022 Partial Approval JOHN KIDWELL
Underground Mechanical 10/5/2022 Corrections Issued JOHN KIDWELL
PLUMBING-Rough 10/11/2022 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 10/18/2022 Order to Comply Issued VINCENT HANLEY
HVAC-Rough 10/18/2022 Partial Approval VINCENT HANLEY
Insulation 10/18/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 11/10/2022 Approved PETER FOLLING
ELECTRICAL-Rough 11/10/2022 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Approved PETER FOLLING
HVAC-Rough 11/10/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 11/10/2022 Approved PETER FOLLING
Wood Frame 11/10/2022 Approved PETER FOLLING
Deputy Reinf. Concrete 11/14/2022 Conditional Approval SEAN WIRCH
Drywall Nailing 11/22/2022 Approved PETER FOLLING
Interior/Exterior Lathing 11/22/2022 Partial Approval PETER FOLLING
ELECTRICAL-Final 2/21/2023 Approved TROY SANDERS
Final 2/21/2023 Permit Finaled TROY SANDERS
HVAC-Final 2/21/2023 Approved TROY SANDERS
PLUMBING-Final 2/21/2023 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 2/21/2023 SGSOV Approved TROY SANDERS
Smoke Detectors 2/21/2023 Approved TROY SANDERS