15286 W SUTTON ST 1-18 91403
Certificate Information: 15286 W SUTTON ST 1-18 91403
- Application / Permit
- 22016-10000-05599
- Plan Check / Job No.
- B22LA03367
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- *ePLAN* CONVERSION OF 1,416 SQ FT PORTION OF GARAGE IN (E) APARTMENT W/ATT GARAGE FOR 3 (N) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(C)
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- CofO Issued on 7/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2022 | LAMAR DAVIS |
| Corrections Issued | 3/30/2022 | LAMAR DAVIS |
| Quality Review Completed | 4/6/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 5/12/2022 | LAMAR DAVIS |
| Plan Check Approved | 5/19/2022 | LAMAR DAVIS |
| Issued | 5/24/2022 | APPLICANT |
| CofO in Progress | 7/1/2024 | BRIAN KELLY |
| CofO Issued | 7/1/2024 | JEFFREY DURAN |
| Permit Finaled | 7/1/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 4/11/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 4/11/2022 | CHRIS CHAHBAZ |
| Grading Pre-Inspection | Cleared | 5/19/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Working Hands Builders; Lic. No.: 1059742-B | 22778 CASS AVENUE WOODLAND HILLS, CA 91364 |
| Engineer | Deihimi,, Amir Hossein; Lic. No.: C78194 | 23172 PLAZA POINTE DR STE 145 LAGUNA HILLS, CA 92653 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/14/2022 | Conditional Approval | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 7/22/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 7/22/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 7/26/2022 | Partial Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 7/26/2022 | Partial Approval | DANIEL VARNUM |
| Excavation/Setback/Form/Re-Bar | 8/16/2022 | Approved | DANIEL VARNUM |
| Footing/Foundation/Slab | 8/16/2022 | Approved | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 8/17/2022 | Conditional Approval | JEFFREY DURAN |
| Wood Frame | 9/16/2022 | Corrections Issued | DANIEL VARNUM |
| Wood Frame | 9/26/2022 | Corrections Issued | ANDREW DORSO |
| Wood Frame | 9/28/2022 | Partial Inspection | DANIEL VARNUM |
| Insulation | 10/5/2022 | Corrections Issued | ANDREW DORSO |
| Insulation | 10/18/2022 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 6/1/2023 | Corrections Issued | JEFFREY FULTON |
| Drywall Nailing | 6/2/2023 | Approved | BRIAN KELLY |
| Interior/Exterior Lathing | 6/5/2023 | Approved | BRIAN KELLY |
| Wood Frame | 6/5/2023 | Partial Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 7/5/2023 | Corrections Issued | BRIAN KELLY |
| Footing/Foundation/Slab | 7/7/2023 | Approved | STEVEN LEVITT |
| Final | 8/31/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Green Building Final | 8/31/2023 | Partial Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 8/31/2023 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 8/31/2023 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 9/6/2023 | Approved | STEVEN LEVITT |
| Final | 6/25/2024 | Partial Inspection | BRIAN KELLY |
| Green Building Final | 6/25/2024 | Approved | BRIAN KELLY |
| Smoke Detectors | 6/25/2024 | Approved | BRIAN KELLY |
| Final | 7/1/2024 | OK to Issue CofO | BRIAN KELLY |