17510 1/2 W TRIBUNE ST 91344
Certificate Information: 17510 1/2 W TRIBUNE ST 91344
- Application / Permit
- 22016-10000-05189
- Plan Check / Job No.
- B22LA03116
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING ACCESSORY LIVING QUARTER TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable parts of LAMC 12.22 A.33 (c)-(d), (g). ATTACHED GARAGE TO REMAIN.
- Permit Issued
- Issued on 5/25/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | GEORGE ALVAREZ |
| Corrections Issued | 3/7/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 4/21/2022 | JAD BASMA |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| Plan Check Approved | 4/29/2022 | GEORGE ALVAREZ |
| Issued | 5/25/2022 | APPLICANT |
| CofO in Progress | 10/12/2022 | DAVID SCANTLIN |
| Permit Finaled | 11/21/2022 | JOHN JANSON |
| CofO Issued | 11/21/2022 | JOHN JANSON |
| Permit Finaled | 11/21/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/25/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/25/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/25/2022 | LEE GUILBEAUX |
| ZA Case | Cleared | 3/25/2022 | MAYELA VILLA |
| Public Works-Highway Ded. | Cleared | 3/25/2022 | LEE GUILBEAUX |
| Tenant Habitability Plan | Cleared | 4/26/2022 | ISMAEL HERNANDEZ |
Contact Information
| Architect | , ; Lic. No.: C33608 | 10801 NATIONAL BLVD SUITE #602 LOS ANGELES, CA 90064 |
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/16/2022 | Approved | DAVID SCANTLIN |
| Final | 6/16/2022 | Corrections Issued | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 6/16/2022 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 6/16/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 7/13/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 7/13/2022 | Approved | DAVID SCANTLIN |
| Final | 7/27/2022 | Partial Inspection | KRISTEN CAUSEY |
| Final | 8/9/2022 | Partial Inspection | KRISTEN CAUSEY |
| Final | 10/11/2022 | OK to Issue CofO | DAVID SCANTLIN |