355 S GRAND AVE 27TH FLR 90071
Certificate Information: 355 S GRAND AVE 27TH FLR 90071
- Application / Permit
- 22016-10000-05173
- Plan Check / Job No.
- B22LA03107
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Interior, non-structural tenant improvement to (E) the 27th floor (22,823 SF). Scope of work to include partitions, ceiling grid, finishes, and millwork. New breakroom at existing office (1,860 SF, 124 occupants). No change in overall use.
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Current Status
- CofO Issued on 4/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2022 | ZAW HAN |
| Corrections Issued | 3/7/2022 | ZAW HAN |
| Applicant returned to address corrections | 3/17/2022 | GEORGE ALVAREZ |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| Applicant returned to address corrections | 5/23/2022 | CHRISTOPHER KOMANCHECK |
| Plan Check Approved | 5/26/2022 | GEORGE ALVAREZ |
| Issued | 6/10/2022 | APPLICANT |
| TCO Issued (Expire Date: 03-12-2023) | 9/13/2022 | ERNESTO CORRAL |
| CofO in Progress | 4/6/2023 | TIMOTHY POWELL |
| CofO Issued | 4/6/2023 | TIMOTHY GRIFFITH |
| Permit Finaled | 4/6/2023 | TIMOTHY GRIFFITH |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/11/2022 | YI LU |
| Fire Marshal Fire Life Safety | Cleared | 4/14/2022 | OSCAR SALGADO JR |
Contact Information
| Architect | Macrae,, Peter S; Lic. No.: C28571 | 74 ORCHARD DRIVE WORTHINGTON, OH 430853657 |
| Contractor | Unispace Contracting Inc; Lic. No.: 940969-B | 1 POST OFFICE SQUARE 37TH FLR BOSTON, MA 02109 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 6/13/2022 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 6/17/2022 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 6/17/2022 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 7/22/2022 | Approved | TIMOTHY BUXTON |
| T-Bar Ceiling | 7/22/2022 | Approved | TIMOTHY BUXTON |
| Final | 8/26/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 8/26/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Rough | 8/26/2022 | Approved | TIMOTHY BUXTON |
| Reinforced Concrete Frame | 8/26/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 8/26/2022 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 8/26/2022 | Approved | TIMOTHY BUXTON |
| Verify Sprinkler Sign Off | 8/26/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 9/2/2022 | OK for TCO | TIMOTHY BUXTON |
| Green Building Final | 9/2/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Reinforced Concrete Frame | 9/2/2022 | Approved | TIMOTHY BUXTON |
| Verify Sprinkler Sign Off | 9/2/2022 | Approved | TIMOTHY BUXTON |
| Special/Order Compliance | 2/15/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 4/6/2023 | OK to Issue CofO | TIMOTHY POWELL |
| Green Building Final | 4/6/2023 | Approved | TIMOTHY POWELL |