5609 S BROADWAY 90037
Certificate Information: 5609 S BROADWAY 90037
- Application / Permit
- 22016-10000-05167
- Plan Check / Job No.
- B22LA03102
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- Change of use from pre-shcool building to a church layout (fixed seating) with new ADA ramp. "COMPLY WITH DEPARTMENT ORDER effective date 05/22/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 3/28/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | TU HUA |
| Corrections Issued | 5/13/2022 | TU HUA |
| Disabled Access Plans Picked Up | 5/13/2022 | APPLICANT |
| Quality Review Completed | 5/18/2022 | KEN GILL |
| Plan Check Approved | 12/13/2023 | TU HUA |
| Issued | 3/28/2024 | APPLICANT |
| Permit Finaled | 11/21/2025 | ADAM BURGESS |
| CofO Issued | 11/21/2025 | ADAM BURGESS |
| Permit Finaled | 11/21/2025 | ADAM BURGESS |
Permit Application Clearance Information
| CPC | Cleared | 6/23/2022 | RYAN LY |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 8/2/2022 | STEVE MELGAR |
| Community Plan Implem. Overlay | Cleared | 11/9/2022 | HELEN JADALI |
| ZI | Cleared | 11/9/2022 | HELEN JADALI |
| ZI | Cleared | 11/17/2022 | DAVID URITA |
| DAS Clearance | Cleared | 12/5/2023 | TU HUA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/12/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 4/18/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 4/18/2024 | Approved | DARRYL ARNOLD |
| Special/Order Compliance | 6/5/2024 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 12/9/2024 | Partial Approval | ALFREDO LOPEZ |
| Final | 12/9/2024 | Partial Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 12/9/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Pre-Inspection | 2/12/2025 | Corrections Issued | DARRYL ARNOLD |
| Drywall Nailing | 3/6/2025 | Approved | RONALD JIMENEZ |
| Final | 3/6/2025 | Conditional Approval | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 3/6/2025 | Approved | RONALD JIMENEZ |
| Final | 5/9/2025 | Partial Inspection | ALFREDO LOPEZ |
| Pre-Inspection | 9/29/2025 | Corrections Issued | DARRYL ARNOLD |
| Final | 10/3/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 10/9/2025 | Conditional Approval | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 10/9/2025 | Approved | ALFREDO LOPEZ |
| Order to Comply | 10/23/2025 | Not Required | DARRYL ARNOLD |
| Special/Order Compliance | 10/23/2025 | Approved | DARRYL ARNOLD |
| Final | 11/14/2025 | Conditional Approval | DARRYL ARNOLD |