3537 S CLARINGTON AVE 90034

Certificate Information: 3537 S CLARINGTON AVE 90034

Application / Permit
22016-10000-05053
Plan Check / Job No.
B22LA03036
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePlan CREATE TWO ATTACHED ACCESSORY DWELLING UNITS PER STATE LAW CA Govt. Code 65852.2(e)(1)(C) BY CONVERTING EXISTING GARAGES
Permit Issued
Issued on 2/3/2023
Issuing Office
Current Status
CofO Issued on 11/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 2/23/2022 MONICA RAMIREZ
Corrections Issued 2/23/2022 MONICA RAMIREZ
Applicant returned to address corrections 6/4/2022 DANIEL SANJUAN
Plan Check Approved 7/17/2022 JOSEPH RAFOLS
Issued 2/3/2023 APPLICANT
CofO in Progress 10/2/2023 FARHAD DADBIN
Permit Finaled 11/1/2023 DAVID TSAU
CofO Issued 11/1/2023 DAVID TSAU
Permit Finaled 11/1/2023 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 2/26/2022 JOSE HERNANDEZ
Sewer availability Cleared 2/26/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 2/28/2022 JOSE HERNANDEZ
Specific Plan Cleared 2/28/2022 PABLO ESTRADA
ZI Cleared 2/28/2022 PABLO ESTRADA
ZI Cleared 2/28/2022 PABLO ESTRADA
Tenant Habitability Plan Cleared 3/4/2022 ISMAEL HERNANDEZ
Grading Pre-Inspection Cleared 3/9/2022 VASIL MIHALEV
Permit Cleared 4/21/2022 CATHERINE ADROVER
Fire Marshal Fire Life Safety Cleared 4/26/2022 ANDREW KO
Specific Plan Cleared 5/4/2022 FREDDY GARCIA
Trees in Parkway Cleared 5/19/2022 ADALBERTO VERA

Contact Information

Contractor Ramirez Construction; Lic. No.: 1071904-B 41101 166TH ST EAST      LANCASTER, CA 93535

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/10/2023 Approved PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Approved FARHAD DADBIN
Footing/Foundation/Slab 3/20/2023 Approved FARHAD DADBIN
Deputy Reinf. Concrete 3/23/2023 Approved FARHAD DADBIN
Deputy Steel/Welding 3/28/2023 Approved FARHAD DADBIN
Wall Anchors 4/3/2023 Not Ready for Inspection FARHAD DADBIN
Wood Frame 4/3/2023 Not Ready for Inspection FARHAD DADBIN
Wood Frame 4/25/2023 Approved FARHAD DADBIN
Insulation 4/27/2023 Approved FARHAD DADBIN
Drywall Nailing 5/1/2023 Approved FARHAD DADBIN
Interior/Exterior Lathing 5/1/2023 Approved FARHAD DADBIN
Interior/Exterior Lathing 5/3/2023 Approved FARHAD DADBIN
Final 9/15/2023 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 9/15/2023 SGSOV Approved FARHAD DADBIN
Smoke Detectors 9/15/2023 Partial Approval FARHAD DADBIN
Final 10/2/2023 OK to Issue CofO FARHAD DADBIN
Smoke Detectors 10/2/2023 Approved FARHAD DADBIN