3108 W SCOTLAND ST 90039
Certificate Information: 3108 W SCOTLAND ST 90039
- Application / Permit
- 22016-10000-05052
- Plan Check / Job No.
- B22LA03035
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) DETACHED GARAGE INTO ADU PER CA GC 65852.2(e)(1)(A).
- Permit Issued
- Issued on 5/17/2022
- Issuing Office
- Current Status
- CofO Issued on 10/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2022 | VIVIAN LAO |
| Corrections Issued | 2/24/2022 | VIVIAN LAO |
| Plan Check Approved | 3/9/2022 | VIVIAN LAO |
| Issued | 5/17/2022 | APPLICANT |
| CofO in Progress | 10/11/2022 | JOSEPH MCGARRY |
| Permit Finaled | 10/29/2022 | DEROLD HAUFF |
| CofO Issued | 10/29/2022 | DEROLD HAUFF |
| Permit Finaled | 10/29/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 3/1/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2022 | CHRISTOPHER ROCHA |
| Grading Pre-Inspection | Cleared | 3/2/2022 | VASIL MIHALEV |
Contact Information
| Contractor | New Generation Home Improvements Inc; Lic. No.: 938552-B | 5805 WHITE OAK AVE #18431 ENCINO, CA 91416 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/8/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/8/2022 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 6/8/2022 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/29/2022 | Partial Inspection | JOSEPH MCGARRY |
| Green Building Rough | 6/29/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/15/2022 | No Access for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/15/2022 | No Access for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/20/2022 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/20/2022 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/16/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/16/2022 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 8/16/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 8/16/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 8/16/2022 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/16/2022 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/16/2022 | Approved | JOSEPH MCGARRY |
| Sewer | 8/16/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/19/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 8/19/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/19/2022 | Approved | JOSEPH MCGARRY |
| Shower Pan | 8/19/2022 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 9/6/2022 | Approved | JOSEPH MCGARRY |
| Gas Test | 9/8/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 10/4/2022 | SGSOV Not Ready | JOSEPH MCGARRY |
| Final | 10/5/2022 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 10/5/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 10/5/2022 | Approved | JOSEPH MCGARRY |