8114 S VERMONT AVE 90044

Certificate Information: 8114 S VERMONT AVE 90044

Application / Permit
22016-10000-05040
Plan Check / Job No.
B22LA03028
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
ePlan Convert existing retail into medical clinic/offices
Permit Issued
Issued on 1/17/2023
Issuing Office
Current Status
CofO Issued on 5/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 LUKE GONZALES
Corrections Issued 5/20/2022 LUKE GONZALES
Applicant returned to address corrections 7/7/2022 LUKE GONZALES
Applicant returned to address corrections 8/3/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 10/5/2022 LAWRENCE QUIRANTE
Plan Check Approved 10/6/2022 FERNANDO FLORES
Issued 1/17/2023 APPLICANT
CofO in Progress 5/21/2024 ALFREDO LOPEZ
CofO Issued 5/28/2024 ERNESTO CORRAL
Permit Finaled 5/28/2024 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/21/2022 TREVOR QUAN
Sewer availability Cleared 6/21/2022 TREVOR QUAN
Community Plan Implem. Overlay Cleared 6/27/2022 RAFAEL FONTES
Community Plan Implem. Overlay Cleared 8/10/2022 RAFAEL FONTES
Historic Resource Verification Cleared 8/11/2022 MAX LODER
Redevelopment Project Area Cleared 8/19/2022 SUSAN WONG

Contact Information

Architect Collins,, Lance Addison; Lic. No.: C30647 101 WEST SPRING STREET # A      LONG BEACH, CA 90806
Contractor Marquis Construction Inc; Lic. No.: 398448-B 5595 DANIELS ST STE E      CHINO, CA 91710

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/24/2023 Approved MARTIN TAVITIAN
Light Gage Steel Frame 3/15/2023 Not Ready for Inspection ALAN MORELOS
Drywall Nailing 4/25/2023 Partial Approval MARTIN TAVITIAN
Insulation 4/25/2023 Approved MARTIN TAVITIAN
Drywall Nailing 5/4/2023 Corrections Issued DARRYL ARNOLD
T-Bar Ceiling 5/10/2023 Not Ready for Inspection MARTIN TAVITIAN
T-Bar Ceiling 6/16/2023 Not Ready for Inspection ALAN MORELOS
T-Bar Ceiling 9/13/2023 Approved MARTIN TAVITIAN
Final 12/14/2023 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 12/14/2023 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 12/14/2023 Not Ready for Inspection LUIS CCAMACHO
Final 3/26/2024 Conditional Approval ALFREDO LOPEZ
Smoke Detectors 3/26/2024 Approved ALFREDO LOPEZ
Wood Frame 3/26/2024 Approved ALFREDO LOPEZ
Final 5/20/2024 OK to Issue CofO ALFREDO LOPEZ