2003-2007 S PENMAR AVE 90291

Certificate Information: 2003-2007 S PENMAR AVE 90291

Application / Permit
22016-10000-04928
Plan Check / Job No.
B22LA02996
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT EXISTING 7 CAR GARAGE ATTACHED TO AN (E) 10 UNIT 2 STORY APARTMENT BUILDING INTO 2 ADUS TOTALING 1,176 SF (MANDATORY SOFT STORY RETROFIT TO BE OBTAINED UNDER SEPARATE PERMIT)
Permit Issued
Issued on 2/15/2024
Issuing Office
Current Status
CofO Corrected on 5/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2022 APPLICANT
Disabled Access Plans Picked Up 3/14/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 HERNAN ARREOLA
Green Plans Picked Up 3/21/2022 APPLICANT
Corrections Issued 3/31/2022 HERNAN ARREOLA
Quality Review Completed 4/6/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 4/8/2022 APPLICANT
Applicant returned to address corrections 2/9/2023 HERNAN ARREOLA
Plan Check Approved 2/8/2024 HERNAN ARREOLA
Issued 2/15/2024 APPLICANT
CofO in Progress 4/23/2024 FARHAD DADBIN
CofO Issued-Status Void 4/23/2024 DAVID TSAU
Permit Finaled-Status Void 4/23/2024 DAVID TSAU
Re-Activate Permit 5/2/2024 DAVID TSAU
Permit Finaled 5/23/2024 DAVID TSAU
CofO Corrected 5/23/2024 DAVID TSAU
Permit Finaled 5/23/2024 DAVID TSAU

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/8/2023 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 2/17/2023 TRACY TATE
Sewer availability Cleared 2/17/2023 TRACY TATE
Address approval Cleared 2/21/2023 TRACY TATE
"Q" conditions Cleared 4/6/2023 SPENCER WEJROWSKI
Specific Plan Cleared 4/18/2023 ALESSANDRO MERCURI
Green Code Cleared 5/23/2023 MICHAEL AYERS
Tenant Habitability Plan Cleared 6/20/2023 HUGO GARRIDO GARZA

Contact Information

Contractor Concord Construction Inc; Lic. No.: 1077056-B 449 SOUTH BEVERLY DRIVE   1ST FLOOR    BEVERLY HILLS, CA 90212

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 2/21/2024 Partial Approval FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 2/21/2024 Approved FARHAD DADBIN
Footing/Foundation/Slab 2/21/2024 Approved FARHAD DADBIN
Green Building Rough 2/21/2024 Approved FARHAD DADBIN
Insulation 2/21/2024 Approved FARHAD DADBIN
Interior/Exterior Lathing 2/21/2024 Partial Inspection FARHAD DADBIN
Wood Frame 2/21/2024 Approved FARHAD DADBIN
Drywall Nailing 2/23/2024 Not Ready for Inspection FARHAD DADBIN
Interior/Exterior Lathing 2/23/2024 Not Ready for Inspection FARHAD DADBIN
Drywall Nailing 3/27/2024 Approved FARHAD DADBIN
Final 3/27/2024 Not Ready for Inspection FARHAD DADBIN
Green Building Final 3/27/2024 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 3/27/2024 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 3/27/2024 Approved FARHAD DADBIN
Final 4/1/2024 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Not Ready FARHAD DADBIN
Final 4/10/2024 OK to Issue CofO FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Approved FARHAD DADBIN