3038 W ATWATER AVE 90039
Certificate Information: 3038 W ATWATER AVE 90039
- Application / Permit
- 22016-10000-04863
- Plan Check / Job No.
- B22LA02923
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE INTO ADU PER STATE LAW GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 6/15/2022
- Issuing Office
- Current Status
- CofO Issued on 12/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2022 | JOE VO |
| Corrections Issued | 2/23/2022 | JOE VO |
| Plan Check Approved | 3/23/2022 | JOE VO |
| Issued | 6/15/2022 | APPLICANT |
| CofO in Progress | 12/2/2022 | CHARLES BOGHOSKHAN |
| CofO Issued | 12/5/2022 | DEROLD HAUFF |
| Permit Finaled | 12/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/28/2022 | MAYELA VILLA |
| Address approval | Cleared | 3/1/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 3/1/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2022 | ABEL CASILLAS |
Contact Information
| Contractor | New Generation Home Improvements Inc; Lic. No.: 938552-B | 5805 WHITE OAK AVE #18431 ENCINO, CA 91416 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/17/2022 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 6/23/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/29/2022 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/29/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/27/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/27/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/27/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Rough | 7/27/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/27/2022 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/10/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/10/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/10/2022 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 8/10/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/10/2022 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 8/19/2022 | Conditional Approval | CHARLES BOGHOSKHAN |
| Insulation | 9/13/2022 | Approved | OSVALDO PARAMO |
| Wood Frame | 9/13/2022 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/15/2022 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 9/15/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/21/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 10/27/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| MERV13>=Final | 10/27/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/27/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 11/29/2022 | OK to Issue CofO | CHARLES BOGHOSKHAN |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Approved | CHARLES BOGHOSKHAN |