3038 W ATWATER AVE 90039

Certificate Information: 3038 W ATWATER AVE 90039

Application / Permit
22016-10000-04863
Plan Check / Job No.
B22LA02923
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE INTO ADU PER STATE LAW GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 6/15/2022
Issuing Office
Current Status
CofO Issued on 12/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2022 APPLICANT
Assigned to Plan Check Engineer 2/21/2022 JOE VO
Corrections Issued 2/23/2022 JOE VO
Plan Check Approved 3/23/2022 JOE VO
Issued 6/15/2022 APPLICANT
CofO in Progress 12/2/2022 CHARLES BOGHOSKHAN
CofO Issued 12/5/2022 DEROLD HAUFF
Permit Finaled 12/5/2022 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 2/28/2022 MAYELA VILLA
Address approval Cleared 3/1/2022 ABEL CASILLAS
Sewer availability Cleared 3/1/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 3/7/2022 ABEL CASILLAS

Contact Information

Contractor New Generation Home Improvements Inc; Lic. No.: 938552-B 5805 WHITE OAK AVE #18431      ENCINO, CA 91416

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/17/2022 Approved HAMIK HARTOUNIAN
Pre-Inspection 6/23/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/29/2022 Approved HAMIK HARTOUNIAN
Underground Mechanical 6/29/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/27/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/27/2022 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 7/27/2022 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 7/27/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 7/27/2022 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/10/2022 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/10/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 8/10/2022 Approved HAMIK HARTOUNIAN
MERV13>=Rough 8/10/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 8/10/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Corrections Issued HAMIK HARTOUNIAN
Deputy Wood Construction 8/19/2022 Conditional Approval CHARLES BOGHOSKHAN
Insulation 9/13/2022 Approved OSVALDO PARAMO
Wood Frame 9/13/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 9/15/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/15/2022 Approved HAMIK HARTOUNIAN
Shower Pan 9/15/2022 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 9/21/2022 Approved HAMIK HARTOUNIAN
Final 10/27/2022 Partial Inspection HAMIK HARTOUNIAN
MERV13>=Final 10/27/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 10/27/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 10/27/2022 Approved HAMIK HARTOUNIAN
Final 11/29/2022 OK to Issue CofO CHARLES BOGHOSKHAN
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Approved CHARLES BOGHOSKHAN