2744 W TEMPLE ST 90026

Certificate Information: 2744 W TEMPLE ST 90026

Application / Permit
22016-10000-04682
Plan Check / Job No.
B22LA02830
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(23) Other-See Work Description
Work Description
ePlan New Tenant improvement and change of use from manufacturing to music studio/office (This space will be used by employees only and not open to the general public.)
Permit Issued
Issued on 9/23/2022
Issuing Office
Current Status
CofO Issued on 5/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2022 APPLICANT
Assigned to Plan Check Engineer 2/20/2022 GARO TELMI
Corrections Issued 2/21/2022 GARO TELMI
Applicant returned to address corrections 3/11/2022 GARO TELMI
Applicant returned to address corrections 3/15/2022 GARO TELMI
Applicant returned to address corrections 4/1/2022 GARO TELMI
Applicant returned to address corrections 4/5/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 4/27/2022 GARO TELMI
Applicant returned to address corrections 5/21/2022 GEORGE ALVAREZ
Applicant returned to address corrections 6/28/2022 KEVIN MORALES
Applicant returned to address corrections 7/13/2022 KEVIN MORALES
Plan Check Approved 7/22/2022 KEVIN MORALES
Issued 9/23/2022 APPLICANT
CofO in Progress 5/21/2024 JEROME BLACKWOOD
Permit Finaled 5/22/2024 ERNESTO CORRAL
CofO Issued 5/22/2024 ERNESTO CORRAL
Permit Finaled 5/22/2024 ERNESTO CORRAL

Permit Application Clearance Information

Sewer availability Cleared 4/12/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 6/3/2022 AMAAN MALIK
Green Code Cleared 7/15/2022 DONALD CRICHLOW
DAS Clearance Cleared 7/20/2022 GARO TELMI

Contact Information

Architect Oberle,, Christopher Lee; Lic. No.: NA31690       ,
Contractor Fc Owens Builds; Lic. No.: 1096946-B       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 9/27/2022 Approved TIMOTHY BUXTON
Wood Frame 12/22/2022 Partial Inspection TIMOTHY POWELL
Green Building Rough 1/10/2023 Approved KATY RAMIREZ
Wood Frame 1/10/2023 Partial Approval KATY RAMIREZ
Insulation 1/18/2023 Approved RAMAZANALI ALMASI
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Partial Approval JULIAN CAPUCETTI
Drywall Nailing 3/24/2023 Partial Approval KATY RAMIREZ
Wood Frame 8/30/2023 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 9/12/2023 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 9/13/2023 Approved KATY RAMIREZ
Drywall Nailing 9/25/2023 Approved RAMAZANALI ALMASI
Final 5/14/2024 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 5/14/2024 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 5/14/2024 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 5/14/2024 Approved JEROME BLACKWOOD
Wood Frame 5/14/2024 Approved JEROME BLACKWOOD
Final 5/21/2024 OK to Issue CofO JEROME BLACKWOOD
Green Building Final 5/21/2024 Approved JEROME BLACKWOOD