1704 W STONE CANYON ROAD 90077
Certificate Information: 1704 W STONE CANYON ROAD 90077
- Application / Permit
- 22016-10000-04664
- Plan Check / Job No.
- B22LA02816
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL BOTH FLOORS OF (E) 2-STORY SFD WITH GARAGE.
- Permit Issued
- Issued on 4/6/2022
- Issuing Office
- Current Status
- Permit Finaled on 9/20/2024
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 2/25/2022 | LAWRENCE QUIRANTE |
| Plan Check Approved | 3/22/2022 | ADAM HEGAZI |
| Issued | 4/6/2022 | APPLICANT |
| Building Plans Picked Up | 5/24/2022 | APPLICANT |
| Permit Finaled | 9/19/2024 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Select Contractors Inc; Lic. No.: 772406-B | 523 VISTA VALLE TRAIL TOPANGA, CA 90290 |
| Engineer | Behshid,, Farshid; Lic. No.: S4585 | 10866 WIMER COUNTRY ROAD SUNLAND, CA 91040 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 5/25/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 5/25/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 5/25/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 6/16/2022 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 6/16/2022 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 7/14/2022 | Partial Approval | CHRISTOPHER WILSON |
| Final | 7/14/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/1/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 9/29/2022 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 11/3/2022 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 11/8/2022 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 11/14/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Gas Test | 11/22/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 11/22/2022 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/22/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 11/28/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 11/28/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 11/28/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 12/6/2022 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 12/6/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 12/6/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 12/9/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 12/9/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/9/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/12/2022 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 12/12/2022 | Approved | CHRISTOPHER WILSON |
| Insulation | 12/12/2022 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 12/12/2022 | Approved | CHRISTOPHER WILSON |
| Structural Steel Frame | 12/12/2022 | Approved | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 12/12/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 12/13/2022 | Partial Approval | CHRISTOPHER WILSON |
| Insulation | 2/24/2023 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 2/24/2023 | Approved | CHRISTOPHER WILSON |
| Insulation | 3/1/2023 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 3/8/2023 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 5/2/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/2/2023 | Approved | CHRISTOPHER WILSON |
| Gas Test | 9/22/2023 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 9/22/2023 | SGSOV Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 7/17/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 7/17/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Final | 7/17/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Final | 7/17/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Smoke Detectors | 7/17/2024 | Approved | CHRISTOPHER WILSON |
| Final | 9/13/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 9/19/2024 | Permit Finaled | CHRISTOPHER WILSON |
| Smoke Detectors | 9/19/2024 | Approved | CHRISTOPHER WILSON |