1316 W 80TH ST 90044
Certificate Information: 1316 W 80TH ST 90044
- Application / Permit
- 22016-10000-04658
- Plan Check / Job No.
- X22LA02374
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (1) Kitchen (2) bathroom remodel for residential buildings (no structural changes). (12) Window and (1) door change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council (NFRC), is required for doors and windows replaced in all residential buildings, three stories or less, per Section 150.2(b) 1B of Title 24. *DOOR CHANGE OUT IS FOR THE GARAGE* *MEP'S INCLUDED* "Comply with Department Order effective date 7/30/2021."
- Permit Issued
- Issued on 2/16/2022
- Issuing Office
- Current Status
- Permit Finaled on 6/8/2022
Permit Application Status History
| Issued | 2/16/2022 | APPLICANT |
| Permit Finaled | 6/7/2022 | LILIANA PORTILLO |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/10/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 3/10/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 3/10/2022 | Corrections Issued | LILIANA PORTILLO |
| Service/Power Release | 3/12/2022 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 3/15/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 3/15/2022 | Approved | LILIANA PORTILLO |
| Shower Pan | 3/15/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/29/2022 | Approved | LILIANA PORTILLO |
| Insulation | 4/2/2022 | Corrections Issued | JOSEPH MCGARRY |
| Insulation | 4/6/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 4/11/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 5/23/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 5/23/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 5/23/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 5/24/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 5/24/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 5/24/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 5/24/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 6/2/2022 | Approved | LILIANA PORTILLO |
| Final | 6/2/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 6/2/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 6/2/2022 | Approved | LILIANA PORTILLO |
| Final | 6/7/2022 | Permit Finaled | LILIANA PORTILLO |
| HVAC-Final | 6/7/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 6/7/2022 | SGSOV Approved | LILIANA PORTILLO |