1112 1/2 W 60TH ST 90044

Certificate Information: 1112 1/2 W 60TH ST 90044

Application / Permit
22016-10000-04447
Plan Check / Job No.
B22LA02662
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION TO ADU PER ORDINANCE
Permit Issued
Issued on 12/5/2022
Issuing Office
Metro
Current Status
Issued on 12/5/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/16/2022 APPLICANT
Assigned to Plan Check Engineer 2/23/2022 KHUONG TRUONG
Corrections Issued 2/24/2022 KHUONG TRUONG
Building Plans Picked Up 2/28/2022 APPLICANT
Applicant returned to address corrections 4/28/2022 MINA HABILI
Applicant returned to address corrections 7/28/2022 DANIEL SANJUAN
Applicant returned to address corrections 10/14/2022 JOSEPH RAFOLS
Plan Check Approved 12/5/2022 LUKE GONZALES
Issued 12/5/2022 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 11/22/2022 MICHAEL SOTO
Address approval Cleared 12/5/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 12/5/2022 ABEL CASILLAS
Roof/Waste drainage to street Cleared 12/5/2022 ABEL CASILLAS
Sewer availability Cleared 12/5/2022 ABEL CASILLAS

Contact Information

Contractor Ecir Construction; Lic. No.: 904931-B 627 W 80TH ST      LOS ANGELES, CA 90044
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/31/2023 Partial Inspection CRAIG DAVIS
Wood Frame 10/31/2023 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 12/7/2023 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 2/2/2024 Corrections Issued RONNIE MINDANAO
Pre-Inspection 2/6/2024 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 10/11/2024 Approved JOHN QUINTANILLA
Pre-Inspection 10/28/2024 Partial Inspection CRAIG DAVIS
BUILDING-Rough-Frame 1/27/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Corrections Issued BARRY HACHE
Green Building Rough 6/13/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 6/13/2025 Partial Approval BARRY HACHE
Interior/Exterior Lathing 7/10/2025 Partial Approval ANTHONY RAMOS
Excavation/Setback/Form/Re-Bar 7/24/2025 Corrections Issued BARRY HACHE
Excavation/Setback/Form/Re-Bar 8/1/2025 Approved BARRY HACHE
ELECTRICAL-Rough 3/3/2026 Corrections Issued BARRY HACHE
PLUMBING-Rough 3/3/2026 Corrections Issued BARRY HACHE
Shower Pan 3/3/2026 Corrections Issued BARRY HACHE
HVAC-Rough 4/7/2026 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 4/7/2026 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 4/8/2026 Not Ready for Inspection RAUL BARAJAS
Rough-Elec/Plmb/HVAC 4/17/2026 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/22/2026 Approved Pending GreenApproval ALEX COLIN
Insulation 4/22/2026 Approved ALEX COLIN
Drywall Nailing 5/4/2026 Approved ALEX COLIN