8050 S NARDIAN WAY 90045

Certificate Information: 8050 S NARDIAN WAY 90045

Application / Permit
22016-10000-04424
Plan Check / Job No.
B22LA02638
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARGE TO (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 6/8/2022
Issuing Office
Current Status
CofO Issued on 5/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 2/16/2022 DANIEL YIP
Corrections Issued 2/17/2022 DANIEL YIP
Applicant returned to address corrections 3/11/2022 DANIEL YIP
Plan Check Approved 5/15/2022 DANIEL YIP
Issued 6/8/2022 APPLICANT
CofO in Progress 5/24/2023 BOBBY KEY
Permit Finaled 5/30/2023 DANIEL ORRANTE
CofO Issued 5/30/2023 DANIEL ORRANTE
Permit Finaled 5/30/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/12/2022 JOSE HERNANDEZ
Sewer availability Cleared 3/12/2022 JOSE HERNANDEZ
ZA Case Cleared 3/14/2022 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 3/15/2022 JOSE HERNANDEZ
Specific Plan Cleared 3/22/2022 VALERIA CEJA
Construction near power lines Cleared 4/23/2022 RIDWAN HARDY

Contact Information

Contractor Aditan Inc; Lic. No.: 986364-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/16/2022 Partial Inspection BOBBY KEY
Excavation/Setback/Form/Re-Bar 8/2/2022 Partial Approval BOBBY KEY
Footing/Foundation/Slab 8/2/2022 Partial Approval BOBBY KEY
Underground Mechanical 8/2/2022 Partial Approval BOBBY KEY
Footing/Foundation/Slab 8/15/2022 Approved BOBBY KEY
Rough-Elec/Plmb/HVAC 9/26/2022 Conditional Approval BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Approved BOBBY KEY
Wood Frame 9/26/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 11/17/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Approved BOBBY KEY
Insulation 11/17/2022 Approved BOBBY KEY
Interior/Exterior Lathing 11/17/2022 Partial Approval BOBBY KEY
Drywall Nailing 12/20/2022 Approved BOBBY KEY
Final 12/20/2022 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 12/20/2022 Approved BOBBY KEY
Shower Pan 12/20/2022 Approved BOBBY KEY
ELECTRICAL-Final 5/5/2023 Corrections Issued BOBBY KEY
Final 5/5/2023 Corrections Issued BOBBY KEY
HVAC-Final 5/5/2023 Approved BOBBY KEY
PLUMBING-Final 5/5/2023 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 5/5/2023 Approved BOBBY KEY
Final 5/23/2023 OK to Issue CofO BOBBY KEY