1611 W 226TH ST 90501

Certificate Information: 1611 W 226TH ST 90501

Application / Permit
22016-10000-04423
Plan Check / Job No.
B22LA02637
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached garage to Accessory Dwelling Unit.
Permit Issued
Issued on 4/6/2022
Issuing Office
Current Status
CofO Issued on 3/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 JOE VO
Corrections Issued 2/18/2022 JOE VO
Plan Check Approved 4/5/2022 JOE VO
Issued 4/6/2022 APPLICANT
CofO in Progress 12/20/2022 EUGENE CASSIDY
Permit Finaled 3/17/2023 DANIEL ORRANTE
CofO Issued 3/17/2023 DANIEL ORRANTE
Permit Finaled 3/17/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/28/2022 JOSE HERNANDEZ
Sewer availability Cleared 2/28/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 3/2/2022 JOSE HERNANDEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/19/2022 Corrections Issued EUGENE CASSIDY
Green Building Rough 5/19/2022 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 5/19/2022 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 7/26/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 8/5/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/30/2022 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 8/30/2022 Approved EUGENE CASSIDY
Footing/Foundation/Slab 8/30/2022 Approved EUGENE CASSIDY
Drywall Nailing 9/6/2022 Approved EUGENE CASSIDY
Insulation 9/6/2022 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 9/12/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/21/2022 Not Ready for Inspection EUGENE CASSIDY
Final 9/21/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 9/21/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 9/21/2022 Approved EUGENE CASSIDY
METHANE-Final 9/21/2022 Approved EUGENE CASSIDY
METHANE-Rough 9/21/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/21/2022 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 9/21/2022 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 9/30/2022 Approved EUGENE CASSIDY
Final 9/30/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 9/30/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/30/2022 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 9/30/2022 Approved EUGENE CASSIDY
Final 10/19/2022 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/19/2022 SGSOV Approved EUGENE CASSIDY
Final 10/27/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 12/19/2022 Approved EUGENE CASSIDY
Final 12/19/2022 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 12/19/2022 Approved EUGENE CASSIDY
PLUMBING-Final 12/19/2022 Approved EUGENE CASSIDY