25094-25100 S FRAMPTON AVE 25094 90710
Certificate Information: 25094-25100 S FRAMPTON AVE 25094 90710
- Application / Permit
- 22016-10000-04144
- Plan Check / Job No.
- B22LA02418
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan CONVERT EXISTING ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT IN AN EXISTING MULTIFAMILY PER STATE LAW GCS 65852.2(e)(1)(C).
- Permit Issued
- Issued on 12/5/2022
- Issuing Office
- Current Status
- CofO Issued on 4/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | MICHAEL LOPEZ |
| Corrections Issued | 3/4/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 3/9/2022 | SAI KHUM |
| Applicant returned to address corrections | 5/18/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 7/13/2022 | MICHAEL LOPEZ |
| Issued | 12/5/2022 | APPLICANT |
| Permit Finaled | 4/23/2025 | JOEY BUCHANAN |
| CofO Issued | 4/23/2025 | JOEY BUCHANAN |
| Permit Finaled | 4/23/2025 | JOEY BUCHANAN |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2022 | ANA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2022 | ANA VILLA |
| Tenant Habitability Plan | Cleared | 3/15/2022 | ISMAEL HERNANDEZ |
| Sewer availability | Cleared | 3/29/2022 | ANA VILLA |
| "Q" conditions | Cleared | 4/20/2022 | LAUREN PADICK |
| Hydrant and Access approval | Cleared | 4/24/2022 | DWIGHT SANKEY |
| Green Code | Cleared | 6/7/2022 | DONALD CRICHLOW |
Contact Information
| Contractor | Alltime Maintenance Inc; Lic. No.: 1033999-B | 2020 CAMFIELD AVE COMMERCE, CA 90040 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/26/2024 | Conditional Approval | AMANUEL BERHE |
| Footing/Foundation/Slab | 9/26/2024 | Conditional Approval | AMANUEL BERHE |
| Green Building Rough | 11/4/2024 | Approved | JOEY BUCHANAN |
| METHANE-Rough | 11/4/2024 | Approved | JOEY BUCHANAN |
| Wood Frame | 11/4/2024 | No Access for Inspection | JOEY BUCHANAN |
| Wood Frame | 11/13/2024 | Approved | MICHAEL PETRUSKO |
| Deputy Wood Construction | 11/20/2024 | Conditional Approval | JOEY BUCHANAN |
| Insulation | 11/25/2024 | Conditional Approval | MICHAEL PETRUSKO |
| Drywall Nailing | 12/3/2024 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 1/3/2025 | Approved | MICHAEL PETRUSKO |
| Final | 1/23/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Green Building Final | 1/23/2025 | Approved | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 1/23/2025 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 2/19/2025 | Conditional Approval | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Approved | MICHAEL PETRUSKO |
| Smoke Detectors | 2/19/2025 | Approved | MICHAEL PETRUSKO |