2157 N VINE ST 90068
Certificate Information: 2157 N VINE ST 90068
- Application / Permit
- 22016-10000-04040
- Plan Check / Job No.
- B22LA02349
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING (4) SPECIAL CANTILEVERED COLUMNS , (1) 2-BAY ORDINARY MOMENT FRAME & (1) WOOD SHEAR WALL.
- Permit Issued
- Issued on 10/7/2022
- Issuing Office
- Current Status
- CofC Issued on 2/14/2024
Permit Application Status History
| Submitted | 2/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | HANS SANTIAGO |
| Corrections Issued | 3/11/2022 | VARAND SARKISIAN |
| Quality Review Completed | 3/11/2022 | SAI KHUM |
| Plan Check Approved | 6/1/2022 | VARAND SARKISIAN |
| No Progress | 7/31/2022 | ANDREW SANTIAGO |
| Plan Check Approved | 8/9/2022 | ANDREW SANTIAGO |
| Plan Check Approved | 9/8/2022 | ANDREW SANTIAGO |
| Issued | 10/7/2022 | APPLICANT |
| OK for CofC | 2/14/2024 | WINSTON DUNNING |
| CofC Issued | 2/14/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/28/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Retrofit 1; Lic. No.: 1003868-B | 19326 VENTURA BLVD STE 200 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: NA68149 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/23/2022 | Not Ready for Inspection | BRUCE CAMPBELL |
| Pre-Inspection | 12/27/2022 | Corrections Issued | VAHE KELEDJIAN |
| Deputy Steel/Welding | 4/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 5/22/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/22/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 6/5/2023 | Corrections Issued | GREGORY POMISH |
| Footing/Foundation/Slab | 6/6/2023 | Approved | GREGORY POMISH |
| Structural Steel Frame | 6/21/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 6/21/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Structural Steel Frame | 7/12/2023 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 7/12/2023 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 7/31/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 8/2/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 8/4/2023 | Approved | VAHE KELEDJIAN |
| Final | 10/2/2023 | Corrections Issued | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 10/2/2023 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 10/2/2023 | Approved | VAHE KELEDJIAN |
| Final | 2/9/2024 | Partial Inspection | WINSTON DUNNING |
| Final | 2/14/2024 | OK for CofC | WINSTON DUNNING |