2836 S GRANVILLE AVE 90064
Certificate Information: 2836 S GRANVILLE AVE 90064
- Application / Permit
- 22016-10000-04009
- Plan Check / Job No.
- B22LA02339
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE OF (E) SFD TO (N) ACCESSORY DWELLING UNIT PER WFPP.
- Permit Issued
- Issued on 5/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2022 | MINA HABILI |
| Corrections Issued | 2/11/2022 | MINA HABILI |
| Applicant returned to address corrections | 4/5/2022 | FERNANDO FLORES |
| Building Plans Picked Up | 4/15/2022 | APPLICANT |
| Plan Check Approved | 5/5/2022 | MINA HABILI |
| Issued | 5/13/2022 | APPLICANT |
| CofO in Progress | 10/3/2022 | JOHNNY MIRANDA |
| Permit Finaled | 10/25/2022 | KENNETH NAGLE |
| CofO Issued | 10/25/2022 | KENNETH NAGLE |
| Permit Finaled | 10/25/2022 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2022 | DINAH GARIN |
| Sewer availability | Cleared | 4/18/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2022 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/6/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/11/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/26/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Not Ready | JOHNNY MIRANDA |
| Final | 9/9/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 9/9/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/13/2022 | Approved | JOHNNY MIRANDA |
| Final | 9/13/2022 | OK to Issue CofO | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 9/13/2022 | Approved | JOHNNY MIRANDA |