723 N HILL PL 90012
Certificate Information: 723 N HILL PL 90012
- Application / Permit
- 22016-10000-03742
- Plan Check / Job No.
- B22LA02197
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Soft Story retrofit using 3 Cantilever Columns
- Permit Issued
- Issued on 5/9/2022
- Issuing Office
- Current Status
- CofC Issued on 9/29/2022
Permit Application Status History
| Submitted | 2/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | VARAND SARKISIAN |
| Corrections Issued | 2/23/2022 | VARAND SARKISIAN |
| Quality Review Completed | 2/24/2022 | SAI KHUM |
| Plan Check Approved | 3/9/2022 | VARAND SARKISIAN |
| Issued | 5/9/2022 | APPLICANT |
| OK for CofC | 9/28/2022 | BRUCE CAMPBELL |
| CofC Issued | 9/29/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/28/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 19528 VENTURA BLVD #300 TARZANA, CA 91356 |
| Engineer | Yiu,, Siu Fung; Lic. No.: S5801 | PO BOX 5143 EL MONTE, CA 91734 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/31/2022 | Corrections Issued | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 6/15/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 6/15/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 6/15/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 6/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Other (see comments) | 6/22/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 6/28/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 6/28/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 6/28/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 6/30/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 7/5/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 7/21/2022 | Approved | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 7/29/2022 | Corrections Issued | BRUCE CAMPBELL |
| Final | 9/28/2022 | OK for CofC | BRUCE CAMPBELL |
| METHANE-Final | 9/28/2022 | Approved | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Approved | BRUCE CAMPBELL |
| Smoke Detectors | 9/28/2022 | Approved | BRUCE CAMPBELL |