6368 W 85TH PL 90045

Certificate Information: 6368 W 85TH PL 90045

Application / Permit
22016-10000-03712
Plan Check / Job No.
B22LA02186
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 2/24/2022
Issuing Office
Current Status
CofO Issued on 3/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2022 APPLICANT
Assigned to Plan Check Engineer 2/9/2022 CARLOS MONTES
Corrections Issued 2/10/2022 CARLOS MONTES
Plan Check Approved 2/18/2022 CARLOS MONTES
Issued 2/24/2022 APPLICANT
CofO in Progress 3/21/2023 HERBERT GIRON
Permit Finaled 3/24/2023 DANIEL ORRANTE
CofO Issued 3/24/2023 DANIEL ORRANTE
Permit Finaled 3/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 2/15/2022 MIGUEL GAMBOA
Address approval Cleared 2/16/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/16/2022 JEANIE LAM
Sewer availability Cleared 2/16/2022 JEANIE LAM
Specific Plan Cleared 2/16/2022 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 1171 JUSTIN AVE APT 3      GLENDALE, CA 91201

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/16/2022 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 3/16/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 3/16/2022 Corrections Issued JESUS RODRIGUEZ
Pre-Inspection 3/16/2022 Not Ready for Inspection JESUS RODRIGUEZ
Sewer 3/16/2022 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 3/21/2022 Conditional Approval JESUS RODRIGUEZ
Sewer 3/21/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 4/7/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 4/7/2022 Corrections Issued DAVID FEILER
Green Building Rough 4/7/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 4/7/2022 Approved DAVID FEILER
Underground Mechanical 4/7/2022 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 4/11/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 4/11/2022 Approved JESUS RODRIGUEZ
Green Building Rough 4/11/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 4/11/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 4/11/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 4/11/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/12/2022 Approved JESUS RODRIGUEZ
Insulation 4/14/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 4/22/2022 Approved DAVID FEILER
Excavation/Setback/Form/Re-Bar 5/26/2022 Not Ready for Inspection RICHARD STEINBACH
Insulation 8/5/2022 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 3/13/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 3/13/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 3/15/2023 Approved HERBERT GIRON
ELECTRICAL-Final 3/15/2023 Approved HERBERT GIRON
Final 3/15/2023 Corrections Issued HERBERT GIRON
Gas Test 3/15/2023 Approved HERBERT GIRON
Green Building Final 3/15/2023 Approved HERBERT GIRON
Green Building Rough 3/15/2023 Approved HERBERT GIRON
HVAC-Final 3/15/2023 Approved HERBERT GIRON
PLUMBING-Final 3/15/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/15/2023 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 3/15/2023 Approved HERBERT GIRON
Final 3/21/2023 OK to Issue CofO HERBERT GIRON
PLUMBING-Final 3/21/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Approved HERBERT GIRON