3103 S LELAND ST 90731

Certificate Information: 3103 S LELAND ST 90731

Application / Permit
22016-10000-03648
Plan Check / Job No.
B22LA02140
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL BOTH FLOORS OF (E) 2-STORY SFD. INCLUDES EXTERIOR ALTERATIONS.
Permit Issued
Issued on 7/8/2022
Issuing Office
Metro
Current Status
Permit Finaled on 11/9/2022

Permit Application Status History

Submitted 2/7/2022 APPLICANT
Assigned to Plan Check Engineer 2/15/2022 LAWRENCE QUIRANTE
Corrections Issued 2/16/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 4/20/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 4/25/2022 APPLICANT
Plan Check Approved 7/8/2022 DANIEL SANJUAN
Issued 7/8/2022 APPLICANT
Permit Finaled 11/9/2022 ANSON MAGLASANG

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/10/2022 JONATHAN HOM
Coastal Zone Cleared 6/23/2022 ANACANY HURTADO

Contact Information

Contractor C S General Contracting Inc; Lic. No.: 947524-B 2654 VIEWRIDGE DR      CHINO HILLS, CA 91709
Engineer Farah,, Moheb Dawod; Lic. No.: C51477 1245 DEXBURY CIR      CORONA, CA 92882

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/14/2022 Corrections Issued ANSON MAGLASANG
Footing/Foundation/Slab 7/14/2022 Approved ANSON MAGLASANG
HVAC-Rough 7/14/2022 Approved ANSON MAGLASANG
PLUMBING-Rough 7/14/2022 Approved ANSON MAGLASANG
Wood Frame 7/14/2022 Conditional Approval ANSON MAGLASANG
Insulation 7/20/2022 Approved ANSON MAGLASANG
Drywall Nailing 7/28/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 7/28/2022 Partial Approval ANSON MAGLASANG
Shower Pan 7/28/2022 Approved ANSON MAGLASANG
ELECTRICAL-Final 10/29/2022 Approved DAVID FEILER
ELECTRICAL-Final 10/29/2022 Off-Hour Fees Due
Final 10/29/2022 Corrections Issued DAVID FEILER
Final 10/29/2022 Off-Hour Fees Due
PLUMBING-Final 10/29/2022 Approved DAVID FEILER
PLUMBING-Final 10/29/2022 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 10/29/2022 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 10/29/2022 SGSOV Not Ready DAVID FEILER
Smoke Detectors 10/29/2022 Off-Hour Fees Due
Smoke Detectors 10/29/2022 Partial Inspection DAVID FEILER
ELECTRICAL-Final 11/9/2022 Approved ANSON MAGLASANG
Final 11/9/2022 Permit Finaled ANSON MAGLASANG
PLUMBING-Final 11/9/2022 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Approved ANSON MAGLASANG
Smoke Detectors 11/9/2022 Approved ANSON MAGLASANG