1126 1/2 W 56TH ST 90037
Certificate Information: 1126 1/2 W 56TH ST 90037
- Application / Permit
- 22016-10000-03625
- Plan Check / Job No.
- B22LA02128
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT REAR GARAGE AND A SLEEPING ROOM TO AN ADU. REPLACE (E) ROOF FRAMING. CEILING JOISTS, DAMAGE WALLS AND CONCRETE SLAB IN GARAGE. PER CA GOVT CODE 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/13/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | SAM CHANG |
| Corrections Issued | 6/1/2022 | SAM CHANG |
| Quality Review Completed | 6/6/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 6/27/2022 | APPLICANT |
| Plan Check Approved | 9/20/2022 | SAM CHANG |
| Issued | 4/13/2023 | APPLICANT |
| CofO in Progress | 10/2/2024 | CRAIG DAVIS |
| Permit Finaled | 11/16/2024 | DEROLD HAUFF |
| CofO Issued | 11/16/2024 | DEROLD HAUFF |
| Permit Finaled | 11/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 7/1/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 7/1/2022 | JEANETTE VONG |
| CPC | Cleared | 7/6/2022 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2022 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 8/29/2022 | GILBERT URREA |
| Green Code | Cleared | 9/20/2022 | SAM CHANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/2/2023 | Partial Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 5/23/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/25/2023 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 5/31/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/27/2023 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 6/27/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 6/27/2023 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 6/27/2023 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 6/29/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 7/11/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 7/11/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 7/11/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 7/12/2023 | Partial Approval | SABAS ALONSO |
| Insulation | 7/21/2023 | Corrections Issued | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/24/2023 | Approved | MICHAEL LEWIS |
| Insulation | 7/24/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 7/24/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 7/26/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/26/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 8/3/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/14/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Final | 8/19/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 8/19/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 8/19/2024 | Partial Approval | CRAIG DAVIS |
| Final | 9/13/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 9/13/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 9/13/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 9/19/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Final | 10/1/2024 | Approved | CRAIG DAVIS |
| Final | 10/1/2024 | OK to Issue CofO | CRAIG DAVIS |
| HVAC-Final | 10/1/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 10/1/2024 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | CRAIG DAVIS |
| Smoke Detectors | 10/1/2024 | Approved | CRAIG DAVIS |
| Pre-Inspection | 10/16/2024 | Approved | CRAIG DAVIS |