6568 W 85TH ST 90045
Certificate Information: 6568 W 85TH ST 90045
- Application / Permit
- 22016-10000-03606
- Plan Check / Job No.
- B22LA02110
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION TO ADU 2 OF 2
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2022 | ZAW HAN |
| Corrections Issued | 2/22/2022 | ZAW HAN |
| Applicant returned to address corrections | 4/20/2022 | TSE MING HUANG |
| Building Plans Picked Up | 4/29/2022 | APPLICANT |
| Issued | 5/2/2022 | APPLICANT |
| CofO in Progress | 12/8/2022 | HERBERT GIRON |
| CofO in Progress | 12/8/2022 | HERBERT GIRON |
| Permit Finaled | 12/13/2022 | DANIEL ORRANTE |
| CofO Issued | 12/13/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/13/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2022 | STEVEN JIN |
| Sewer availability | Cleared | 2/26/2022 | STEVEN JIN |
| CPC | Cleared | 3/8/2022 | DALIA MOKAYED |
| CPC | Cleared | 3/8/2022 | DALIA MOKAYED |
| CPC | Cleared | 3/8/2022 | DALIA MOKAYED |
| Construction near power lines | Cleared | 3/14/2022 | NADER ISKANDER |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 4/7/2022 | JENSON LEE |
| Specific Plan | Cleared | 4/7/2022 | EDUARDO HERMOSO |
Contact Information
| Contractor | Nandco Construction; Lic. No.: 1044615-B | 4836 FULTON AVE SHERMAN OAKS, CA 91423 |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 18759 WILLOWTREE LANE PORTER RANCH, CA 91326 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/13/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Partial Approval | JESUS RODRIGUEZ |
| Gas Test | 6/28/2022 | Partial Approval | JESUS RODRIGUEZ |
| Rough-Elec/Plmb/HVAC | 6/28/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Sewer | 6/28/2022 | Partial Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 6/28/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Wood Construction | 7/20/2022 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/21/2022 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 7/21/2022 | Partial Approval | HERBERT GIRON |
| Special/Order Compliance | 7/21/2022 | Approved | ANDREW NAVE |
| Insulation | 8/1/2022 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 8/1/2022 | Not Ready for Inspection | HERBERT GIRON |
| Insulation | 8/5/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 8/5/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/10/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 8/10/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 8/10/2022 | Corrections Issued | HERBERT GIRON |
| Rough-Elec/Plmb/HVAC | 8/10/2022 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 8/10/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 9/9/2022 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 10/4/2022 | Partial Approval | CLAYTON GRAHAM |
| ELECTRICAL-Final | 10/27/2022 | Corrections Issued | HERBERT GIRON |
| Final | 10/27/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 10/27/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 10/27/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 10/27/2022 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 10/27/2022 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 10/27/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 11/1/2022 | Approved | HERBERT GIRON |
| Final | 11/1/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 11/1/2022 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/1/2022 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/1/2022 | SGSOV Approved | HERBERT GIRON |
| Final | 12/5/2022 | OK to Issue CofO | HERBERT GIRON |