5416-5418 W SMILEY DR 90016

Certificate Information: 5416-5418 W SMILEY DR 90016

Application / Permit
22016-10000-03427
Plan Check / Job No.
B22LA01770
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan: INTERIOR REMODEL TO (E) 1-STORY DUPLEX
Permit Issued
Issued on 6/1/2022
Issuing Office
Current Status
CofO Issued on 7/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2022 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 DANIEL YIP
Corrections Issued 2/4/2022 DANIEL YIP
Applicant returned to address corrections 4/13/2022 DANIEL YIP
Plan Check Approved 5/26/2022 DANIEL YIP
No Progress 6/1/2022 DANIEL YIP
Plan Check Approved 6/1/2022 DANIEL YIP
Issued 6/1/2022 APPLICANT
CofO in Progress 7/17/2023 JOSE AVILA
Permit Finaled 7/25/2023 DEROLD HAUFF
CofO Issued 7/25/2023 DEROLD HAUFF
Permit Finaled 7/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 4/6/2022 MICHAEL SOTO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 6/24/2022 Corrections Issued JOSE AVILA
Pre-Inspection 6/24/2022 Corrections Issued JOSE AVILA
Drywall Nailing 7/7/2022 Partial Approval JOSE AVILA
Insulation 7/7/2022 Corrections Issued JOSE AVILA
Special/Order Compliance 8/1/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 8/4/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Corrections Issued JOSE AVILA
Green Building Rough 8/17/2022 Corrections Issued JOSE AVILA
Wood Frame 8/25/2022 Corrections Issued JOSE AVILA
Wood Frame 9/2/2022 Partial Approval JOSE AVILA
Insulation 9/12/2022 Approved JOSE AVILA
Drywall Nailing 9/15/2022 Corrections Issued JOSE AVILA
Special/Order Compliance 1/3/2023 Approved JOSE AVILA
Interior/Exterior Lathing 1/12/2023 Approved JOSE AVILA
Pre-Inspection 3/1/2023 Corrections Issued JOSE AVILA
Final 4/11/2023 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/11/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 4/11/2023 Approved JOSE AVILA
Final 4/18/2023 Corrections Issued JOSE AVILA
Final 5/1/2023 Partial Inspection JOSE AVILA
Final 7/13/2023 OK to Issue CofO JOSE AVILA
Wood Frame 7/13/2023 Approved JOSE AVILA