3914 W 9TH ST 90019

Certificate Information: 3914 W 9TH ST 90019

Application / Permit
22016-10000-03349
Plan Check / Job No.
B22LA01945
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ADDITION TO (E) DETACHED GARAGE AND CONVER THE ENTIRE BUILDING TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 5/3/2022
Issuing Office
Current Status
CofO Issued on 3/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2022 APPLICANT
Assigned to Plan Check Engineer 2/8/2022 DANIEL YIP
Corrections Issued 2/9/2022 DANIEL YIP
Plan Check Approved 4/6/2022 DANIEL YIP
Plan Check Approved 5/3/2022 DANIEL YIP
Issued 5/3/2022 APPLICANT
CofO in Progress 2/28/2023 ALIZAH MAYAGOITIA
Permit Finaled 3/2/2023 DEROLD HAUFF
CofO Issued 3/2/2023 DEROLD HAUFF
Permit Finaled 3/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/17/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 2/23/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 2/23/2022 CHRISTOPHER ROCHA
Low Impact Development Cleared 3/8/2022 ANTHONY VARGAS
HPOZ Cleared 3/10/2022 AMANDA KAINER
Roof/Waste drainage to street Cleared 3/11/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Goliath Construction; Lic. No.: 1056541-B 6914 RADFORD AVE      NORTH HOLLYWOOD, CA 91605
Engineer Hernandez,, Gerardo; Lic. No.: C78115 1426 E STUART AVE      WEST COVINA, CA 91791

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/10/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 6/10/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 6/10/2022 Partial Approval ALIZAH MAYAGOITIA
Underground Mechanical 6/10/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 6/15/2022 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/15/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 8/12/2022 Corrections Issued JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 8/12/2022 Approved JEFFREY MEAD
ELECTRICAL-Rough 8/17/2022 Approved JEFFREY MEAD
PLUMBING-Rough 8/17/2022 Corrections Issued JEFFREY MEAD
HVAC-Rough 8/19/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 8/24/2022 Approved JEFFREY MEAD
Green Building Rough 8/24/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 8/24/2022 Approved JEFFREY MEAD
Wood Frame 8/24/2022 Approved JEFFREY MEAD
Insulation 8/30/2022 Approved JEFFREY MEAD
Drywall Nailing 9/2/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 9/2/2022 Approved JEFFREY MEAD
Shower Pan 9/2/2022 Approved JEFFREY MEAD
Underground Mechanical 12/21/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 2/23/2023 Approved ALIZAH MAYAGOITIA
Final 2/23/2023 Conditional Approval ALIZAH MAYAGOITIA
Green Building Final 2/23/2023 Approved ALIZAH MAYAGOITIA
HVAC-Final 2/23/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 2/23/2023 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Not Required ALIZAH MAYAGOITIA
Smoke Detectors 2/23/2023 Approved ALIZAH MAYAGOITIA
Final 2/27/2023 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 2/27/2023 Approved ALIZAH MAYAGOITIA