4151 W PROSPECT AVE 90027
Certificate Information: 4151 W PROSPECT AVE 90027
- Application / Permit
- 22016-10000-03141
- Plan Check / Job No.
- B22LA01823
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- EXISTING 2-STORY OFFICE W/ BASEMENT (BLDG A.): INTERIOR TENANT IMPROVEMENT OF BF, 1F AND 2F. PARTIAL DEMOLITION OF EXISTING INTERIOR NON-STRUCTURAL PARTITIONS AND CEILINGS ON BF. DEMOLITION OF EXISTING INTERIOR NON-STRUCTURAL PARTITIONS AND CEILINGS ON 1F AND 2F. PROPOSED NON-STRUCTURAL PARTITIONS, CEILINGS, FLOORS, FINSIHES AND FURNITURE. PROPOSED ACCESSIBLE ALL-GENDER RESTROOMS ON BF, 1F AND 2F. PROPOSED FALL-PROTECTION RAILING AT ROOF.
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/15/2024
Permit Application Status History
| Submitted | 2/3/2022 | APPLICANT |
| Green Plans Picked Up | 2/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | ALBERT SERVIN |
| Disabled Access Plans Picked Up | 2/18/2022 | APPLICANT |
| Corrections Issued | 2/23/2022 | ALBERT SERVIN |
| Quality Review Completed | 2/23/2022 | PETER KIM |
| Building Plans Picked Up | 3/2/2022 | APPLICANT |
| Applicant returned to address corrections | 4/27/2022 | ALBERT SERVIN |
| Plan Check Approved | 5/18/2022 | ALBERT SERVIN |
| Issued | 8/25/2022 | APPLICANT |
| Permit Finaled | 5/14/2024 | RAFAEL CORTES |
Permit Application Clearance Information
| "D" conditions | Cleared | 3/2/2022 | RUBEN VASQUEZ |
| "Q" conditions | Cleared | 3/2/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 3/2/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 3/2/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 3/2/2022 | RUBEN VASQUEZ |
| Green Code | Cleared | 4/26/2022 | AARON COSTA |
| DAS Clearance | Cleared | 4/28/2022 | SHINE LIN |
Contact Information
| Architect | Spence,, Brian Kerrigan; Lic. No.: C34200 | 453 SOUTH SPRING STREET STE 408 LOS ANGELES, CA 90013 |
| Contractor | Gray West Construction Inc; Lic. No.: 775947-B | 421 E CERRITOS AVENUE ANAHEIM, CA 92805 |
| Engineer | Rogowski,, Benjamin Andrew; Lic. No.: S6559 | 950 S GRAND AVE 4TH FLOOR LOS ANGELES, CA 90015 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/31/2022 | Approved | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 9/12/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 9/14/2022 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 9/14/2022 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 9/16/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Deputy Reinf. Concrete | 9/19/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Fireproofing | 10/13/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 11/9/2022 | Partial Approval | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 12/1/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Light Gage Steel Frame | 12/1/2022 | Partial Approval | MARK FERRARI |
| Reinforced Concrete Frame | 12/2/2022 | Approved | JONATHAN QUACH |
| Insulation | 12/6/2022 | Partial Inspection | RAFAEL CORTES |
| Insulation | 12/8/2022 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 12/15/2022 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 12/16/2022 | Approved | JONATHAN QUACH |
| Drywall Nailing | 12/30/2022 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 1/3/2023 | Corrections Issued | RONALD JIMENEZ |
| Deputy Drilled-In Anchors | 1/4/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 1/4/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 1/5/2023 | Conditional Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 1/5/2023 | Partial Approval | TIMOTHY POWELL |
| Deputy Reinf. Concrete | 1/6/2023 | Conditional Approval | KATY RAMIREZ |
| Drywall Nailing | 1/6/2023 | Partial Inspection | KATY RAMIREZ |
| Light Gage Steel Frame | 2/3/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 2/8/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 2/9/2023 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 2/13/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Drywall Nailing | 2/15/2023 | Partial Approval | VAHE KELEDJIAN |
| T-Bar Ceiling | 2/23/2023 | Partial Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 3/7/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Drywall Nailing | 4/20/2023 | Partial Approval | VAHE KELEDJIAN |
| Light Gage Steel Frame | 4/20/2023 | Partial Approval | VAHE KELEDJIAN |
| Insulation | 5/3/2023 | Approved | VAHE KELEDJIAN |
| Drywall Nailing | 5/22/2023 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 6/1/2023 | Partial Approval | TIMOTHY POWELL |
| Deputy Reinf. Concrete | 6/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 7/12/2023 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 7/12/2023 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 7/20/2023 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 7/27/2023 | Partial Approval | VAHE KELEDJIAN |
| Drywall Nailing | 7/31/2023 | Partial Inspection | GREGORY POMISH |
| T-Bar Ceiling | 7/31/2023 | Not Ready for Inspection | GREGORY POMISH |
| T-Bar Ceiling | 8/2/2023 | Conditional Approval | MARTIN TAVITIAN |
| Drywall Nailing | 8/8/2023 | No Access for Inspection | MARTIN TAVITIAN |
| Light Gage Steel Frame | 8/8/2023 | No Access for Inspection | MARTIN TAVITIAN |
| Light Gage Steel Frame | 8/9/2023 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 8/10/2023 | Approved | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Partial Approval | RAFAEL CORTES |
| Structural Steel Frame | 9/29/2023 | No Access for Inspection | VAHE KELEDJIAN |
| T-Bar Ceiling | 9/29/2023 | No Access for Inspection | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 10/27/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Interior/Exterior Lathing | 11/3/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Final | 1/31/2024 | Corrections Issued | KATY RAMIREZ |
| Green Building Final | 1/31/2024 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Gas Company | KATY RAMIREZ |
| Smoke Detectors | 1/31/2024 | Not Ready for Inspection | KATY RAMIREZ |
| Special/Order Compliance | 2/2/2024 | Corrections Issued | KATY RAMIREZ |
| Pre-Inspection | 2/9/2024 | Approved | RAFAEL CORTES |
| Light Gage Steel Frame | 3/28/2024 | Partial Approval | RAFAEL CORTES |
| Final | 4/4/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 4/4/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Smoke Detectors | 4/4/2024 | Approved | RAFAEL CORTES |
| Pre-Inspection | 4/18/2024 | Approved | RAFAEL CORTES |
| Pre-Inspection | 4/26/2024 | Approved | RAFAEL CORTES |
| Final | 5/14/2024 | Permit Finaled | RAFAEL CORTES |
| Green Building Final | 5/14/2024 | Approved | RAFAEL CORTES |