11 E 27TH AVE 1-11 90291
Certificate Information: 11 E 27TH AVE 1-11 90291
- Application / Permit
- 22016-10000-03135
- Plan Check / Job No.
- B22LA01816
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- TO CONVERT AN EXISTING 466.22 SQ.FT. RECREATION ROOM INTO A NEW ACCESSORY DWELLING UNIT. Per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/8/2022
- Issuing Office
- Current Status
- CofO Issued on 9/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2022 | KHUONG TRUONG |
| Corrections Issued | 2/12/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 2/14/2022 | APPLICANT |
| Applicant returned to address corrections | 5/27/2022 | FERNANDO FLORES |
| Plan Check Approved | 6/1/2022 | JOSEPH RAFOLS |
| Issued | 6/8/2022 | APPLICANT |
| CofO in Progress | 9/11/2023 | AMANUEL BERHE |
| Permit Finaled | 9/18/2023 | DAVID TSAU |
| CofO Issued | 9/18/2023 | DAVID TSAU |
| Permit Finaled | 9/18/2023 | DAVID TSAU |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/15/2022 | PEDRO AYALA |
| Tenant Habitability Plan | Cleared | 4/27/2022 | ISMAEL HERNANDEZ |
| Address approval | Cleared | 5/10/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 5/16/2022 | JENSON LEE |
| Coastal Zone | Cleared | 5/24/2022 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 5/24/2022 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 5/24/2022 | MARITZA PRZEKOP |
| Specific Plan | Cleared | 5/24/2022 | MARITZA PRZEKOP |
| ZI | Cleared | 5/24/2022 | MARITZA PRZEKOP |
Contact Information
| Contractor | D C O Real Estate Inc; Lic. No.: 1078972-B | 415 AVONDALE AVE LOS ANGELES, CA 90049 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/11/2023 | Partial Approval | FARHAD DADBIN |
| METHANE-Rough | 3/31/2023 | Approved | FARHAD DADBIN |
| Wood Frame | 3/31/2023 | Approved | FARHAD DADBIN |
| Drywall Nailing | 4/4/2023 | Approved | FARHAD DADBIN |
| Interior/Exterior Lathing | 4/7/2023 | Approved | FARHAD DADBIN |
| Final | 9/6/2023 | Partial Approval | AMANUEL BERHE |
| SGSOV-Seismic Gas S/O Valve | 9/6/2023 | SGSOV Approved | AMANUEL BERHE |
| Smoke Detectors | 9/6/2023 | Approved | AMANUEL BERHE |
| Final | 9/11/2023 | OK to Issue CofO | AMANUEL BERHE |