2224 W MARICOPA DR 90065

Certificate Information: 2224 W MARICOPA DR 90065

Application / Permit
22016-10000-03092
Plan Check / Job No.
B22LA01772
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* INTERIOR REMODEL TO (E) SFD
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
Permit Finaled on 8/6/2024

Permit Application Status History

Submitted 2/4/2022 APPLICANT
Assigned to Plan Check Engineer 2/7/2022 VIVIAN LAO
Corrections Issued 2/7/2022 VIVIAN LAO
Plan Check Approved 3/4/2022 VIVIAN LAO
Issued 3/10/2022 APPLICANT
Permit Finaled 8/5/2024 LILIANA PORTILLO

Permit Application Clearance Information

Specific Plan Cleared 2/16/2022 NASHYA JENSEN
Sewer availability Cleared 2/22/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 2/23/2022 CINDY QI
Grading Pre-Inspection Cleared 3/4/2022 VIVIAN LAO

Contact Information

Contractor Right Choice Home Remodeling Inc The; Lic. No.: 1066456-B       ,
Contractor The Right Choice Home Remodeling Inc; Lic. No.: 1066456-B       ,
Engineer Grigoryan,, Souren Krist; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 5/9/2022 Partial Inspection HAMIK HARTOUNIAN
Wood Frame 5/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/23/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 5/23/2022 Approved OSVALDO PARAMO
Wood Frame 5/23/2022 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 9/8/2022 No Access for Inspection HAMIK HARTOUNIAN
Final 9/8/2022 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/8/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 9/8/2022 No Access for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/27/2022 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 10/27/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/16/2023 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/18/2024 Approved BRIAN SULLIVAN
Final 7/18/2024 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 7/18/2024 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 7/18/2024 Approved BRIAN SULLIVAN
Final 8/5/2024 Permit Finaled LILIANA PORTILLO