6351 W 84TH ST 90045

Certificate Information: 6351 W 84TH ST 90045

Application / Permit
22016-10000-02983
Plan Check / Job No.
B22LA01745
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DETACHED STORAGE AREA (ZC: 193 SF) TO ADU AND ADDITION (ZC: 161 SF) PER CA GC 65852.2(e)(1)(B) AND LAMC 12.22.A.33(c)-(d), (g). (E) DETACHED 2-CAR GARAGE TO REMAIN.
Permit Issued
Issued on 1/28/2023
Issuing Office
Current Status
CofO Issued on 9/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2022 APPLICANT
Assigned to Plan Check Engineer 2/2/2022 VIVIAN LAO
Corrections Issued 2/3/2022 VIVIAN LAO
Applicant returned to address corrections 2/10/2022 VIVIAN LAO
Applicant returned to address corrections 4/21/2022 VIVIAN LAO
Plan Check Approved 9/14/2022 VIVIAN LAO
Issued 1/28/2023 APPLICANT
CofO in Progress 9/25/2023 BOBBY KEY
Permit Finaled 9/28/2023 DANIEL ORRANTE
CofO Issued 9/28/2023 DANIEL ORRANTE
Permit Finaled 9/28/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/18/2022 NIKTA MOUSAVI
Address approval Cleared 4/19/2022 DINAH GARIN
Miscellaneous Cleared 4/21/2022 RAYMOND MUGAMBWA
Miscellaneous Cleared 4/26/2022 FREDDY GARCIA
Construction within easement Cleared 6/3/2022 RIDWAN HARDY
Sewer availability Cleared 7/1/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 9/12/2022 VLADIMIR ARUTYUNYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801
Engineer Ni,, Zhang Yuan; Lic. No.: NA68149       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/25/2023 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 4/25/2023 Approved BOBBY KEY
PLUMBING-Rough 4/25/2023 Partial Approval BOBBY KEY
Sewer 4/25/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Partial Approval RICHARD STEINBACH
ELECTRICAL-Rough 6/21/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 6/21/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 6/21/2023 Approved HERBERT GIRON
ELECTRICAL-Rough 6/28/2023 Approved RICHARD STEINBACH
HVAC-Rough 6/28/2023 Approved RICHARD STEINBACH
PLUMBING-Rough 6/28/2023 Corrections Issued RICHARD STEINBACH
BUILDING-Rough-Frame 7/3/2023 Approved BOBBY KEY
Green Building Rough 7/3/2023 Approved BOBBY KEY
PLUMBING-Rough 7/3/2023 Approved BOBBY KEY
Insulation 7/5/2023 Corrections Issued HERBERT GIRON
Drywall Nailing 7/10/2023 Approved HERBERT GIRON
Shower Pan 7/19/2023 Corrections Issued HERBERT GIRON
Shower Pan 7/21/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 7/25/2023 Approved RICHARD STEINBACH
Service/Power Release 8/4/2023 Corrections Issued HERBERT GIRON
Special/Order Compliance 8/4/2023 Partial Inspection JESUS PINEDA
ELECTRICAL-Final 9/25/2023 Approved BOBBY KEY
Final 9/25/2023 OK to Issue CofO BOBBY KEY
Green Building Final 9/25/2023 Approved BOBBY KEY
HVAC-Final 9/25/2023 Approved BOBBY KEY
PLUMBING-Final 9/25/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/25/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 9/25/2023 Approved BOBBY KEY