541 W SOLANO AVE 90012
Certificate Information: 541 W SOLANO AVE 90012
- Application / Permit
- 22016-10000-02846
- Plan Check / Job No.
- B22LA01640
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY SEISMIC RETROFIT PER LABC CH. 93 USING A SPECIAL STEEL CANTILEVER COLUMN
- Permit Issued
- Issued on 6/22/2023
- Issuing Office
- Metro
- Current Status
- CofC Issued on 9/26/2023
Permit Application Status History
| Submitted | 1/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | VARAND SARKISIAN |
| Corrections Issued | 3/1/2022 | VARAND SARKISIAN |
| Quality Review Completed | 3/2/2022 | SAI KHUM |
| Building Plans Picked Up | 3/7/2022 | APPLICANT |
| Plan Check Approved | 6/22/2023 | VARAND SARKISIAN |
| Issued | 6/22/2023 | APPLICANT |
| OK for CofC | 9/21/2023 | VAHE KELEDJIAN |
| CofC Issued | 9/26/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 6/20/2023 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | R L G Construction; Lic. No.: 1023091-B | 5730 LA MIRADA AVENUE LOS ANGELES, CA 90038 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 7/17/2023 | Partial Approval | VAHE KELEDJIAN |
| Deputy Drilled-In Anchors | 8/3/2023 | Conditional Approval | VAHE KELEDJIAN |
| Excavation/Setback/Form/Re-Bar | 8/3/2023 | Partial Inspection | VAHE KELEDJIAN |
| Wood Frame | 8/3/2023 | Approved | VAHE KELEDJIAN |
| Excavation/Setback/Form/Re-Bar | 8/4/2023 | Conditional Approval | VAHE KELEDJIAN |
| Deputy Wood Construction | 8/8/2023 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/9/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 8/11/2023 | Partial Approval | JEROME BLACKWOOD |
| Final | 9/20/2023 | Partial Inspection | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Not Ready | VAHE KELEDJIAN |
| Smoke Detectors | 9/20/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Final | 9/21/2023 | OK for CofC | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 9/21/2023 | Approved | VAHE KELEDJIAN |