1035 S CONCORD ST 90023
Certificate Information: 1035 S CONCORD ST 90023
- Application / Permit
- 22016-10000-02834
- Plan Check / Job No.
- B22LA01630
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing storage building to ADU and add bathroom CONNECTING TO AN (E) DETACHED GARAGE TO CREATE A DETACHED ADU PER ORDINANCE
- Permit Issued
- Issued on 4/10/2022
- Issuing Office
- Current Status
- CofO Issued on 10/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2022 | CARLOS MONTES |
| Corrections Issued | 2/2/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 2/10/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 2/18/2022 | CARLOS MONTES |
| Plan Check Approved | 2/23/2022 | CARLOS MONTES |
| Issued | 4/10/2022 | APPLICANT |
| CofO in Progress | 10/12/2023 | FREDDIE RIVERA |
| Permit Finaled | 10/14/2023 | DEROLD HAUFF |
| CofO Issued | 10/14/2023 | DEROLD HAUFF |
| Permit Finaled | 10/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 2/7/2022 | ISMAEL HERNANDEZ |
| Address approval | Cleared | 2/9/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 2/9/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2022 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 2/10/2022 | ROBERT HUGHES |
| Sewer availability | Cleared | 2/10/2022 | JEANETTE VONG |
Contact Information
| Architect | , ; Lic. No.: C39413 | 4341 RUSSELL AVE LOS ANGELES, CA 90631 |
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/5/2022 | Conditional Approval | FREDDIE RIVERA |
| Pre-Inspection | 8/5/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 9/1/2022 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/8/2022 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 9/8/2022 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 9/8/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 9/29/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 9/29/2022 | Conditional Approval | FREDDIE RIVERA |
| Insulation | 9/29/2022 | Partial Inspection | FREDDIE RIVERA |
| Wood Frame | 9/29/2022 | Approved | FREDDIE RIVERA |
| Insulation | 10/25/2022 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 11/1/2022 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 12/19/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 6/22/2023 | Approved | FREDDIE RIVERA |
| Final | 6/22/2023 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/22/2023 | Approved | FREDDIE RIVERA |
| Green Building Final | 6/22/2023 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 6/22/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 6/22/2023 | Not Ready for Inspection | FREDDIE RIVERA |
| MERV13>=Rough | 6/22/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 6/22/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 10/4/2023 | Approved | FREDDIE RIVERA |
| Final | 10/4/2023 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 10/4/2023 | Approved | FREDDIE RIVERA |
| HVAC-Final | 10/4/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 10/4/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 10/10/2023 | Conditional Approval | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/10/2023 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 10/10/2023 | Approved | FREDDIE RIVERA |