2866 S MCCONNELL DR 90064

Certificate Information: 2866 S MCCONNELL DR 90064

Application / Permit
22016-10000-02810
Plan Check / Job No.
B22LA01612
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 4/6/2022
Issuing Office
Current Status
CofO Issued on 5/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2022 APPLICANT
Assigned to Plan Check Engineer 2/1/2022 RAHEL BEYENE
Corrections Issued 2/1/2022 RAHEL BEYENE
Applicant returned to address corrections 3/7/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 4/6/2022 FERNANDO FLORES
Issued 4/6/2022 APPLICANT
Building Plans Picked Up 4/11/2022 APPLICANT
CofO in Progress 5/3/2023 CLAYTON GRAHAM
Permit Finaled 5/4/2023 DANIEL ORRANTE
CofO Issued 5/4/2023 DANIEL ORRANTE
Permit Finaled 5/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/10/2022 JENSON LEE
Sewer availability Cleared 3/1/2022 JENSON LEE
Grading Pre-Inspection Cleared 3/4/2022 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 3/9/2022 JENSON LEE

Contact Information

Contractor Lannen Construction Inc; Lic. No.: 811038-B 1545 SAWTELLE BLVD STE 22      LOS ANGELES, CA 90025

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/2/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 6/2/2022 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 6/6/2022 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 6/6/2022 Partial Approval STEPHANIE SWANSON
Pre-Inspection 6/6/2022 Partial Inspection STEPHANIE SWANSON
Deputy Reinf. Concrete 6/10/2022 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 6/24/2022 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/25/2022 Corrections Issued PATRICK QUALEY
Green Building Rough 7/25/2022 Not Ready for Inspection PATRICK QUALEY
METHANE-Rough 7/25/2022 Approved PATRICK QUALEY
Wood Frame 7/25/2022 Partial Approval PATRICK QUALEY
Deputy Wood Construction 7/27/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Partial Approval OGANES TARAKHCHYAN
Wood Frame 8/11/2022 Partial Approval OGANES TARAKHCHYAN
Green Building Final 8/15/2022 Approved OGANES TARAKHCHYAN
Insulation 8/23/2022 No Access for Inspection OGANES TARAKHCHYAN
Insulation 8/25/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/25/2022 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 9/12/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 9/12/2022 Partial Approval JOHN KIDWELL
Special/Order Compliance 11/8/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Special/Order Compliance 11/14/2022 Approved OGANES TARAKHCHYAN
Final 3/28/2023 Corrections Issued ASHLEY THOMPSON
Green Building Rough 3/28/2023 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 3/28/2023 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 3/28/2023 Approved ASHLEY THOMPSON
Wood Frame 3/28/2023 Approved ASHLEY THOMPSON
Final 4/13/2023 Not Ready for Inspection ASHLEY THOMPSON
Final 4/19/2023 Corrections Issued CLAYTON GRAHAM
Final 4/26/2023 Conditional Approval CLAYTON GRAHAM
Final 5/2/2023 OK to Issue CofO CLAYTON GRAHAM