2626 1/2 W 17TH ST 90019
Certificate Information: 2626 1/2 W 17TH ST 90019
- Application / Permit
- 22016-10000-02654
- Plan Check / Job No.
- B22LA01509
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING DETACHED GARAGE TO ADU WITH ADDITION
- Permit Issued
- Issued on 12/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2022 | JOSEPH RAFOLS |
| Corrections Issued | 6/29/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 7/13/2022 | APPLICANT |
| Applicant returned to address corrections | 9/2/2022 | MINA HABILI |
| Plan Check Approved | 12/9/2022 | WEIJIAN HUANG |
| Issued | 12/9/2022 | APPLICANT |
| CofO in Progress | 8/14/2025 | WILLIAM MICHALAK |
| Permit Finaled | 1/15/2026 | CLAUDIO MORENO |
| CofO Issued | 1/15/2026 | CLAUDIO MORENO |
| Permit Finaled | 1/15/2026 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 7/21/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 11/28/2022 | CINDY QI |
| Sewer availability | Cleared | 12/5/2022 | CINDY QI |
| Community Plan Implem. Overlay | Cleared | 12/6/2022 | KYLE WINSTON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/24/2023 | Approved | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 12/15/2023 | Approved | WILLIAM MICHALAK |
| Rough-Elec/Plmb/HVAC | 1/31/2025 | Corrections Issued | WILLIAM MICHALAK |
| Underground Mechanical | 1/31/2025 | Corrections Issued | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 3/10/2025 | Conditional Approval | LUIS CORRAL |
| Final | 3/10/2025 | Not Ready for Inspection | LUIS CORRAL |
| Footing/Foundation/Slab | 3/10/2025 | Conditional Approval | LUIS CORRAL |
| Green Building Final | 3/10/2025 | Approved | LUIS CORRAL |
| Green Building Rough | 3/10/2025 | Approved | LUIS CORRAL |
| METHANE-Barrier | 3/10/2025 | Not Ready for Inspection | LUIS CORRAL |
| METHANE-Final | 3/10/2025 | Not Ready for Inspection | LUIS CORRAL |
| METHANE-Rough | 3/10/2025 | Not Ready for Inspection | LUIS CORRAL |
| METHANE-Subgrade | 3/10/2025 | Not Ready for Inspection | LUIS CORRAL |
| SGSOV-Seismic Gas S/O Valve | 3/10/2025 | SGSOV Not Required | LUIS CORRAL |
| Smoke Detectors | 3/10/2025 | Approved | LUIS CORRAL |
| METHANE-Rough | 3/14/2025 | Approved | LUIS CORRAL |
| METHANE-Subgrade | 3/14/2025 | Approved | LUIS CORRAL |
| BUILDING-Rough-Frame | 3/18/2025 | Approved | LUIS CORRAL |
| Final | 3/18/2025 | Corrections Issued | LUIS CORRAL |
| Footing/Foundation/Slab | 3/18/2025 | Approved | LUIS CORRAL |
| Final | 3/28/2025 | OK to Issue CofO | LUIS CORRAL |