1720 S BUTLER AVE 90025
Certificate Information: 1720 S BUTLER AVE 90025
- Application / Permit
- 22016-10000-02516
- Plan Check / Job No.
- B22LA01443
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan Supplemental 21016-10000-22576. Increase size of ADU and revise floor plan inside units. NO change to overall sqft of building
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- Permit Finaled on 9/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | HERNAN ARREOLA |
| Corrections Issued | 1/27/2022 | HERNAN ARREOLA |
| Plan Check Approved | 3/8/2022 | HERNAN ARREOLA |
| Issued | 3/15/2022 | APPLICANT |
| Permit Finaled-Status Void | 9/11/2024 | CASIMIR BRITTON |
| Re-Activate Permit | 9/13/2024 | CASIMIR BRITTON |
| Permit Finaled | 9/19/2024 | CASIMIR BRITTON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Retrofit 1; Lic. No.: 1003868-B | 19326 VENTURA BLVD STE 200 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: NA68149 | , |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/26/2022 | Approved | JOHN DODGE |
| Pre-Inspection | 4/28/2022 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 7/11/2022 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 10/25/2022 | Partial Approval | SORIN CIRSTOIU |
| Wood Frame | 2/22/2023 | Approved | MICHAEL PETRUSKO |
| Insulation | 6/1/2023 | Approved | MICHAEL PETRUSKO |
| Interior/Exterior Lathing | 6/1/2023 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 8/4/2023 | Partial Inspection | SORIN CIRSTOIU |
| Drywall Nailing | 8/21/2023 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 8/25/2023 | Approved | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 8/30/2023 | No Access for Inspection | PAUL DAVIDSON |
| Final | 8/19/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 8/19/2024 | SGSOV Not Ready | CASIMIR BRITTON |
| Smoke Detectors | 8/19/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Final | 9/5/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 9/5/2024 | SGSOV Approved | CASIMIR BRITTON |
| Smoke Detectors | 9/5/2024 | Approved | CASIMIR BRITTON |
| Final | 9/11/2024 | Partial Approval | CASIMIR BRITTON |
| Final | 9/19/2024 | Permit Finaled | CASIMIR BRITTON |