624 N LUCERNE BLVD 90004
Certificate Information: 624 N LUCERNE BLVD 90004
- Application / Permit
- 22016-10000-02395
- Plan Check / Job No.
- B22LA01378
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING ONE STORY DETACHED GARAGE (399 sf zoning) INTO ADU (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 8/24/2022
- Issuing Office
- Metro
- Current Status
- Issued on 8/24/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2022 | AUNG SOE |
| Corrections Issued | 2/15/2022 | AUNG SOE |
| Building Plans Picked Up | 4/19/2022 | APPLICANT |
| Plan Check Approved | 8/24/2022 | JOSEPH RAFOLS |
| Issued | 8/24/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/16/2022 | CINDY QI |
| Sewer availability | Cleared | 5/16/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bustillos, Portillo, Alejandro Ivan; Lic. No.: C87257 | 4749 W 169TH STREET LAWNDALE, CA 90260 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/5/2023 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 6/14/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Sewer | 6/15/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 11/29/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 11/29/2023 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 11/29/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/17/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 4/17/2024 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 4/17/2024 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 4/17/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/24/2025 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 6/11/2025 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 6/18/2025 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 6/26/2025 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 7/1/2025 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 7/22/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 7/22/2025 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 7/22/2025 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 8/1/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Underground Mechanical | 11/18/2025 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 11/19/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 11/19/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Underground Mechanical | 11/19/2025 | Approved | JEFFREY MEAD |
| Rough-Elec/Plmb/HVAC | 11/20/2025 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 11/25/2025 | Approved | JEFFREY MEAD |
| Green Building Rough | 11/25/2025 | Approved | JEFFREY MEAD |
| METHANE-Rough | 11/25/2025 | Approved | JEFFREY MEAD |
| Rough-Elec/Plmb/HVAC | 11/25/2025 | Approved | JEFFREY MEAD |
| Insulation | 1/27/2026 | Approved | JEFFREY MEAD |
| Wood Frame | 4/13/2026 | Not Ready for Inspection | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2026 | Approved | JOSH MEISTER |
| Rough-Elec/Plmb/HVAC | 4/16/2026 | Approved | JOSH MEISTER |
| Drywall Nailing | 5/20/2026 | Approved | JEFFREY MEAD |
| Service/Power Release | 5/20/2026 | Not Ready for Inspection | JEFFREY MEAD |