1040 E SUPERBA AVE 90291

Certificate Information: 1040 E SUPERBA AVE 90291

Application / Permit
22016-10000-02201
Plan Check / Job No.
B22LA01283
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO DETACHED ADU PER STATE LAW
Permit Issued
Issued on 3/1/2022
Issuing Office
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2022 APPLICANT
Assigned to Plan Check Engineer 1/28/2022 CARLOS MONTES
Corrections Issued 1/28/2022 CARLOS MONTES
Plan Check Approved 2/18/2022 CARLOS MONTES
Issued 3/1/2022 APPLICANT
CofO in Progress 10/13/2022 DAVID FEILER
Permit Finaled 10/28/2022 DANIEL ORRANTE
CofO Issued 10/28/2022 DANIEL ORRANTE
Permit Finaled 10/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 2/11/2022 HISASHI KOBAYAKAWA
Address approval Cleared 2/16/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 2/16/2022 HISASHI KOBAYAKAWA
Specific Plan Cleared 2/16/2022 PEDRO AYALA

Contact Information

Architect Cho,, Steven B; Lic. No.: NA28986       ,
Contractor Owner-Builder       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/25/2022 Partial Approval PATRICK QUALEY
Underground Mechanical 3/25/2022 Approved PATRICK QUALEY
BUILDING-Rough-Frame 4/5/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 4/5/2022 Corrections Issued STEPHANIE SWANSON
Final 4/5/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 4/5/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 4/5/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 5/9/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 5/9/2022 Approved DAVID FEILER
HVAC-Rough 5/9/2022 Approved DAVID FEILER
PLUMBING-Rough 5/9/2022 Approved DAVID FEILER
Wood Frame 5/9/2022 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 6/24/2022 Approved DAVID FEILER
Green Building Rough 6/24/2022 Approved DAVID FEILER
Verify Sprinkler Sign Off 6/24/2022 Approved DAVID FEILER
Insulation 7/1/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 7/13/2022 Approved DAVID FEILER
Interior/Exterior Lathing 7/26/2022 Approved DAVID FEILER
Shower Pan 7/26/2022 Approved DAVID FEILER
Final 9/20/2022 Corrections Issued DAVID FEILER
Green Building Final 9/20/2022 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/20/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 9/20/2022 Approved DAVID FEILER
Final 10/12/2022 OK to Issue CofO DAVID FEILER