1040 E SUPERBA AVE 90291
Certificate Information: 1040 E SUPERBA AVE 90291
- Application / Permit
- 22016-10000-02201
- Plan Check / Job No.
- B22LA01283
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO DETACHED ADU PER STATE LAW
- Permit Issued
- Issued on 3/1/2022
- Issuing Office
- Current Status
- CofO Issued on 10/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2022 | CARLOS MONTES |
| Corrections Issued | 1/28/2022 | CARLOS MONTES |
| Plan Check Approved | 2/18/2022 | CARLOS MONTES |
| Issued | 3/1/2022 | APPLICANT |
| CofO in Progress | 10/13/2022 | DAVID FEILER |
| Permit Finaled | 10/28/2022 | DANIEL ORRANTE |
| CofO Issued | 10/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/11/2022 | HISASHI KOBAYAKAWA |
| Address approval | Cleared | 2/16/2022 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2022 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 2/16/2022 | PEDRO AYALA |
Contact Information
| Architect | Cho,, Steven B; Lic. No.: NA28986 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/25/2022 | Partial Approval | PATRICK QUALEY |
| Underground Mechanical | 3/25/2022 | Approved | PATRICK QUALEY |
| BUILDING-Rough-Frame | 4/5/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/5/2022 | Corrections Issued | STEPHANIE SWANSON |
| Final | 4/5/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 4/5/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/5/2022 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/9/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 5/9/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 5/9/2022 | Approved | DAVID FEILER |
| PLUMBING-Rough | 5/9/2022 | Approved | DAVID FEILER |
| Wood Frame | 5/9/2022 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 6/24/2022 | Approved | DAVID FEILER |
| Green Building Rough | 6/24/2022 | Approved | DAVID FEILER |
| Verify Sprinkler Sign Off | 6/24/2022 | Approved | DAVID FEILER |
| Insulation | 7/1/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 7/13/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 7/26/2022 | Approved | DAVID FEILER |
| Shower Pan | 7/26/2022 | Approved | DAVID FEILER |
| Final | 9/20/2022 | Corrections Issued | DAVID FEILER |
| Green Building Final | 9/20/2022 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 9/20/2022 | Approved | DAVID FEILER |
| Final | 10/12/2022 | OK to Issue CofO | DAVID FEILER |