459 S LORENA ST 90063

Certificate Information: 459 S LORENA ST 90063

Application / Permit
22016-10000-02187
Plan Check / Job No.
B22LA01271
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
REPAIR EXISTING FRAMING, REPAIR AND REPLACE PLUMBING AND ELECTRICAL, INSTALL DRYWALL, REPAIR AND REPLACE STUCCO, INSTALL RETROFIT WINDOWS, REPLACE INSULATION.
Permit Issued
Issued on 3/7/2022
Issuing Office
Current Status
Permit Finaled on 6/6/2022

Permit Application Status History

Submitted 1/25/2022 APPLICANT
Assigned to Plan Check Engineer 2/1/2022 JOSEPH RAFOLS
Corrections Issued 2/2/2022 JOSEPH RAFOLS
Plan Check Approved 2/23/2022 KHUONG TRUONG
Issued 3/7/2022 APPLICANT
Building Plans Picked Up 3/8/2022 APPLICANT
Permit Finaled 6/3/2022 FREDDIE RIVERA

Permit Application Clearance Information

Tenant Habitability Plan Cleared 2/4/2022 ISMAEL HERNANDEZ
Grading Pre-Inspection Cleared 2/16/2022 PATRICK MISCHLICH

Contact Information

Contractor A M Z Construction Inc; Lic. No.: 1018155-B 13045 TOM WHITE WAY STE G      NORWALK, CA 90650
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/15/2022 Partial Inspection FREDDIE RIVERA
HVAC-Rough 3/15/2022 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 3/15/2022 Partial Inspection FREDDIE RIVERA
Pre-Inspection 3/15/2022 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 3/18/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Approved FREDDIE RIVERA
HVAC-Rough 3/18/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 3/25/2022 Corrections Issued FREDDIE RIVERA
MERV13>=Rough 3/25/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 3/25/2022 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 4/1/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 4/1/2022 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 4/11/2022 Partial Approval FREDDIE RIVERA
Deputy Drilled-In Anchors 4/13/2022 Approved FREDDIE RIVERA
Insulation 4/13/2022 Approved FREDDIE RIVERA
Drywall Nailing 4/15/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/18/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 5/20/2022 Approved FREDDIE RIVERA
Final 5/20/2022 Partial Inspection FREDDIE RIVERA
HVAC-Final 5/20/2022 Approved FREDDIE RIVERA
MERV13>=Final 5/20/2022 Approved FREDDIE RIVERA
PLUMBING-Final 5/20/2022 Conditional Approval FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/20/2022 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 5/20/2022 Approved FREDDIE RIVERA
Final 5/27/2022 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/27/2022 SGSOV Not Ready FREDDIE RIVERA
Final 6/3/2022 Permit Finaled FREDDIE RIVERA