1589 E 47TH ST 90011
Certificate Information: 1589 E 47TH ST 90011
- Application / Permit
- 22016-10000-02091
- Plan Check / Job No.
- B22LA01218
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. VERIFY WORK DONE UNDER ADU CONVERSION PERMIT 21016-20000-54578 USING SIMPSON STRONG WALLS IF IT MEETS THE MINIMUM REQUIREMENT OF SOFT STORY RETROFIT ORDINANCE *(CERTIFICATE OF COMPLIANCE FOR SOFT STORY SHALL NOT BE ISSUED TILL CERTIFICATE OF OCCUPANCYY FOR ADU CONVERSION PERMIT IS OBTAINED)*
- Permit Issued
- Issued on 9/23/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 4/25/2023
Permit Application Status History
| Submitted | 1/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | HANS SANTIAGO |
| Corrections Issued | 2/14/2022 | HANS SANTIAGO |
| Quality Review Completed | 2/15/2022 | SAI KHUM |
| Plan Check Approved | 3/30/2022 | ANDREW SANTIAGO |
| Plan Check Approved | 4/5/2022 | ANDREW SANTIAGO |
| Building Plans Picked Up | 4/25/2022 | APPLICANT |
| Issued | 9/23/2022 | APPLICANT |
| OK for CofC | 4/20/2023 | DARRYL ARNOLD |
| CofC Issued | 4/25/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/19/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Rok Construction; Lic. No.: 639550-B | 15740 SHERMAN WAY # 211 VAN NUYS, CA 91406 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/25/2022 | Corrections Issued | DARRYL ARNOLD |
| Pre-Inspection | 10/26/2022 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 10/31/2022 | Partial Approval | DARRYL ARNOLD |
| Structural Steel Frame | 12/6/2022 | Corrections Issued | DARRYL ARNOLD |
| Structural Steel Frame | 12/12/2022 | Corrections Issued | DARRYL ARNOLD |
| Structural Steel Frame | 12/14/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 12/15/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 12/27/2022 | Partial Approval | ALAN MORELOS |
| Insulation | 12/27/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 1/12/2023 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 1/17/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 3/10/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 4/20/2023 | OK for CofC | DARRYL ARNOLD |