1144 1/2 S HI POINT ST 90035
Certificate Information: 1144 1/2 S HI POINT ST 90035
- Application / Permit
- 22016-10000-01859
- Plan Check / Job No.
- B22LA01056
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE TO NEW ADU (329 SQ.FT.) CONSISTING OF SLEEPING, BATHROOM, KITCHEN AND LIVING. 1 OF 2
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2022 | MINA HABILI |
| Corrections Issued | 2/3/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 4/1/2022 | LUKE GONZALES |
| Applicant returned to address corrections | 4/21/2022 | RACHEL BEYENE |
| Building Plans Picked Up | 4/25/2022 | APPLICANT |
| Plan Check Approved | 7/27/2022 | JOSEPH RAFOLS |
| Issued | 7/27/2022 | APPLICANT |
| CofO in Progress | 11/20/2023 | JOSE AVILA |
| CofO Issued | 11/29/2023 | DEROLD HAUFF |
| Permit Finaled | 11/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2022 | JEANIE LAM |
| Sewer availability | Cleared | 3/1/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2022 | JEANIE LAM |
| CPC | Cleared | 4/15/2022 | DANIEL CORONADO |
| Construction near power lines | Cleared | 6/8/2022 | WALTER RAMIREZ |
| HPOZ | Cleared | 7/20/2022 | JONATHAN KAPLAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chu,, Tien Manh; Lic. No.: C72324 | 9542 PACIFIC AVE ANAHEIM, CA 92804 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/11/2022 | Corrections Issued | JOSE AVILA |
| Special/Order Compliance | 8/24/2022 | Approved | JOSE AVILA |
| Special/Order Compliance | 9/16/2022 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 9/29/2022 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 10/3/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 10/3/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Approved | JOSE AVILA |
| METHANE-Rough | 5/25/2023 | Approved | JOSE AVILA |
| Special/Order Compliance | 6/8/2023 | Approved | JOSE AVILA |
| Insulation | 6/20/2023 | Approved | JOSE AVILA |
| Final | 9/20/2023 | Not Ready for Inspection | JOSE AVILA |
| Final | 10/5/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 10/5/2023 | Approved | JOSE AVILA |
| Green Building Rough | 10/5/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 10/5/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 10/5/2023 | Approved | JOSE AVILA |
| Final | 10/17/2023 | Corrections Issued | JOSE AVILA |
| Wood Frame | 10/17/2023 | Approved | JOSE AVILA |
| Final | 11/20/2023 | OK to Issue CofO | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/20/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 11/20/2023 | Approved | JOSE AVILA |