1429 N LAGOON AVE 90744
Certificate Information: 1429 N LAGOON AVE 90744
- Application / Permit
- 22016-10000-01663
- Plan Check / Job No.
- B22LA00929
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF GARAGE ADDITION TO CREATE ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 4/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2022 | RICARDO RAMIREZ |
| Corrections Issued | 1/25/2022 | RICARDO RAMIREZ |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| Applicant returned to address corrections | 3/13/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 4/25/2022 | RICARDO RAMIREZ |
| Issued | 4/28/2022 | APPLICANT |
| CofO in Progress | 1/3/2023 | EUGENE CASSIDY |
| Permit Finaled | 3/17/2023 | DANIEL ORRANTE |
| CofO Issued | 3/17/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/17/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2022 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 4/7/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 4/11/2022 | JOSE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/19/2022 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 5/19/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Subgrade | 5/19/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 5/19/2022 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/26/2022 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 5/26/2022 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 5/26/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/26/2022 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Partial Approval | EUGENE CASSIDY |
| HVAC-Rough | 7/12/2022 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/19/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/19/2022 | Approved | EUGENE CASSIDY |
| Green Building Rough | 7/19/2022 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 7/19/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 7/19/2022 | Approved | EUGENE CASSIDY |
| Insulation | 7/25/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 8/16/2022 | Approved | EUGENE CASSIDY |
| Final | 11/8/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 11/8/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 11/8/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 11/18/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 11/18/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 11/18/2022 | Approved | EUGENE CASSIDY |
| Final | 11/30/2022 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Final | 1/3/2023 | Approved | EUGENE CASSIDY |
| Final | 1/3/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 1/3/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/3/2023 | Approved | EUGENE CASSIDY |