5839 E YORK BLVD 90042
Certificate Information: 5839 E YORK BLVD 90042
- Application / Permit
- 22016-10000-01662
- Plan Check / Job No.
- B22LA00928
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- CHANGE OF USE FROM RESTAURANT TO RETAIL.
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Current Status
- CofO Issued on 6/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2022 | STANLEY RAAP |
| Corrections Issued | 2/1/2022 | STANLEY RAAP |
| Disabled Access Plans Picked Up | 2/15/2022 | APPLICANT |
| Plan Check Approved | 3/7/2022 | FARSHAD ALIMOHAMADI |
| Issued | 3/9/2022 | APPLICANT |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| CofO in Progress | 6/13/2022 | MARK FERRARI |
| CofO Issued | 6/14/2022 | ERNESTO CORRAL |
| Permit Finaled | 6/14/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| "D" conditions | Cleared | 2/3/2022 | RICHARD REASER |
| Sewer availability | Cleared | 2/23/2022 | KHOUNG LE |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2022 | KHOUNG LE |
| DAS Clearance | Cleared | 3/2/2022 | EDDIE GARIN |
Contact Information
| Architect | Diaz,, Arminda C; Lic. No.: C28977 | 5027 ALMADEN DR LOS ANGELES, CA 90042 |
| Contractor | Moshe Cohen Incorporated; Lic. No.: 762655-B | 18075 VENTURA BLVD STE 135 ENCINO, CA 91316 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 3/14/2022 | Approved | RAFAEL ESPINOZA |
| T-Bar Ceiling | 3/14/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Drywall Nailing | 3/18/2022 | Partial Approval | MARK FERRARI |
| T-Bar Ceiling | 3/18/2022 | Partial Inspection | MARK FERRARI |
| Drywall Nailing | 3/21/2022 | Not Ready for Inspection | MARK FERRARI |
| T-Bar Ceiling | 3/21/2022 | Not Ready for Inspection | MARK FERRARI |
| T-Bar Ceiling | 4/7/2022 | Not Ready for Inspection | MARK FERRARI |
| Final | 5/13/2022 | Partial Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 5/13/2022 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 5/13/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 5/13/2022 | Approved | MARK FERRARI |
| Final | 5/17/2022 | Partial Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 5/17/2022 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 5/17/2022 | Approved | MARK FERRARI |
| Final | 5/25/2022 | Conditional Approval | MARK FERRARI |
| T-Bar Ceiling | 5/25/2022 | Approved | MARK FERRARI |
| Final | 6/13/2022 | Conditional Approval | MARK FERRARI |