1226 S CURSON AVE 90019
Certificate Information: 1226 S CURSON AVE 90019
- Application / Permit
- 22016-10000-01561
- Plan Check / Job No.
- B22LA00824
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New Uncoverred Patio Addition to (E) SFD with 6" lactice spacing per Engineer design
- Permit Issued
- Issued on 6/24/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2022 | DANIEL SANJUAN |
| Corrections Issued | 1/21/2022 | DANIEL SANJUAN |
| Plan Check Approved | 2/6/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 4/15/2022 | APPLICANT |
| Issued | 6/24/2022 | APPLICANT |
| CofO in Progress | 11/16/2023 | JOSE AVILA |
| Permit Finaled | 12/9/2023 | DEROLD HAUFF |
| CofO Issued | 12/9/2023 | DEROLD HAUFF |
| Permit Finaled | 12/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/25/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | JEANIE LAM |
Contact Information
| Architect | Wacht,, Michael Adam; Lic. No.: C33626 | 5919 W. 3RD STREET LOS ANGELES, CA 90036 |
| Contractor | Archetype Inc; Lic. No.: 980164-B | 1072 HOLLYGROVE LN ALTADENA, CA 91001 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/29/2022 | Approved | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 7/28/2022 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/10/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 5/10/2023 | Approved | JOSE AVILA |
| Green Building Final | 5/10/2023 | Approved | JOSE AVILA |
| METHANE-Barrier | 5/10/2023 | Approved | JOSE AVILA |
| METHANE-Final | 5/10/2023 | Approved | JOSE AVILA |
| METHANE-Rough | 5/10/2023 | Approved | JOSE AVILA |
| METHANE-Subgrade | 5/10/2023 | Approved | JOSE AVILA |
| Smoke Detectors | 5/10/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/7/2023 | Approved | JOSE AVILA |
| Final | 6/7/2023 | Partial Inspection | JOSE AVILA |
| Green Building Rough | 6/7/2023 | Approved | JOSE AVILA |
| Final | 10/6/2023 | Corrections Issued | JOSE AVILA |
| Final | 11/16/2023 | OK to Issue CofO | JOSE AVILA |